Hi Frank, I have finished dE/dx calibration, put it in Db.

I am still waiting for testing the calibration with SL24y.

I have submitted test jobs two days ago, but they have not started.

 


                                                              Yuri Fisyak

STAR                                           Phone: +1 631 344 3913
Brookhaven National Laboratory  Fax:    +1 631 344 4206
510A/1-161
http://www.star.bnl.gov/~fisyak       E-mail: fisyak AT bnl.gov

 

 

 

-----Original Message-----
From: Frank Geurts <geurts AT rice.edu>
Date: Tuesday, December 17, 2024 at 3:35PM
To: Fisyak, Yuri V <fisyak AT bnl.gov>
Cc: Star-tpc L <Star-tpc-l AT lists.bnl.gov>
Subject: P24iy production: dE/dx calibrations

Hi Yuri,

 

We are slated to start the P24iy production by the end of this week. Can you remind me what dE/dx calibrations are in place and which ones are still in progress?

 

 

Cheers,

-Frank

 

 