Skip to Content.
Sympa Menu

usatlas-hllhc-l2deputymgmt-nsf-l - [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF ICE sheet, phase-2

usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List

List archive

Chronological Thread  
  • From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • To: "Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
  • Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF ICE sheet, phase-2
  • Date: Fri, 5 Jul 2019 10:36:19 -0400


Hello all,

So-called "phase-1" of the ICE (Independent Cost Estimate) is now coming to a close. After some struggles, we agreed that the BOEs were too complex and that the starting point for the ICE would be a master spreadsheet listing the documents used to
a) explain what the deliverable is, and
b) obtain quotes

Attached is the master sheet, which we need to send to NSF fully filled out on July 15. Therefore, we need you to return it by *COB Thursday July 11*.

The sheet is largely self-explanatory, but the Tile Main Board can serve as an example. What you need to do is

1) Check that I got all the relevant lines, i.e. all the lines that include material costs relevant to deliverable construction

2) Fill out columns H to Q. In many cases I put in educated guesses, these may be wrong. A few specific comments:
*J: this is an index to indicate if multiple payments correspond to a single quote (eg Tile Main Board assembly batches)
*M: make sure you have these documents: in a few more weeks we'll need to provide them so they can get quotes. Looking through the packages put together for our initial attempt, I did not always see gerber files where I expected them)
*O: to my knowledge, only ASICs made under the CERN frame contract only have one possible vendor, but that may be incorrect.
*P: indicate here if you applied any kind of scaling, eg because you used a different board's gerber to get a quote
*Q is about documentation that explains the deliverable, but is not used in obtaining quotes.

Any questions, let us know.

Best,

Gustaaf

Attachment: ICE-large-procurements.xlsx