usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List
List archive
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] ICE sheet, almost final
- From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
- To: John Parsons <parsons AT nevis.columbia.edu>, "Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
- Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] ICE sheet, almost final
- Date: Mon, 15 Jul 2019 11:09:48 +0200
Hi John,
Thanks for spotting this. As much as possible I would like to avoid these 67% numbers. So instead I have removed that text everywhere and changed the number in J7 to 1088 (4x272).
For the ADC, I've changed the text to "Direct cost reflects 66.2% US cost share." as there the cost needs to include the NRE, so scaling down the number of parts doesn't work.
Now, for the lpGBT and VL+:
-lpGBT: according to the BOE 41400 are needed. US share is 55.4%, so we should want 22936. But the sheet you sent has 28140? (I was not able to reverse engineer where the 28140 comes from.) For now, I changed the number to 22936 and added in the comments: (US pays for 55.4% of total needed, ie 22936 of 41400)
-VL+ should be 7645 rather than 9246 you listed. So I did the same thing for now.
BTW, there's a mistake in the BOE: it says that the optics costs are escalated, but the resource used is no escalation. I think no escalation is correct, certainly for lpGBT.
Best,
Gustaaf
On 7/14/19 7:29 PM, John Parsons wrote:
Hi Gustaaf,
For LAr, there is potentially some confusion
for the FEB2 PCB fab and assembly (lines 8 through 15).
You have recalculated the quantity in Col. J, due
to the 67% US cost share. Then the comment in Col. O
includes "cost ... reflects 67% US cost share". It is
not clear whether the 67% could be applied twice, since
you have already reduced the quantity, so the US share
would correspond to 100% of the quantity you list.
Note that for components (line 7), you did it
differently, list the FULL quantity and then including
the 67% cost share in the comment. That seems more
clear (and is inconsistent with the other lines mentioned
above).
I would suggest to list the full quantity in
all cases.
Regards,
John
On 7/13/19 2:05 PM, Gustaaf Brooijmans wrote:
Hello all,
Attached is the almost final ICE sheet. Please look it over. Any problems, let me know by Sunday evening. (I removed some info that is just for us.)
Tom, I think we should put the number of chambers and number of tubes in column J anyway, eg J3 should have the number of chambers for that batch.
Best,
Gustaaf
_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l
--
Gustaaf Brooijmans - Columbia University
@Columbia: (212) 854 4527; Nevis virtual phone: (914) 591 2804
Als sie mich holten,
gab es keinen mehr, der protestieren konnte.
-
[Usatlas-hllhc-l2deputymgmt-nsf-l] ICE sheet, almost final,
Gustaaf Brooijmans, 07/13/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] ICE sheet, almost final,
John Parsons, 07/14/2019
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] ICE sheet, almost final, Gustaaf Brooijmans, 07/15/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] ICE sheet, almost final,
John Parsons, 07/14/2019
Archive powered by MHonArc 2.6.24.