| Hi all, And here's a graphical representation of the schedule float/contingency based on the table Gustaaf sent... A couple of things to note: 1. I've included and extra 1 year (220 working days) addition in the "available float" entries to show the impact of the 1-year LS3 delay. Even without this though, most deliverables have adequate float to cover the simulated need. 2. For those deliverables which don't have adequate float (dark
      blue bar < red bar): 3. You do *not* need to include this graphic in your talks. But
      you can if you find it helpful. Keep in mind though that the
      numbers may change at the last minute - especially for LAr - so if
      you plan to use the graphic, please let me know so I can alert you
      to any changes. Cheers  -  Hal On 7/19/19 7:17 AM, Gustaaf Brooijmans
      wrote: Hello, Here's the contingency presentation sheet. We're still working on confirming the available float for LAr. Best, Gustaaf _______________________________________________ Usatlas-hllhc-l2deputymgmt-nsf-l mailing list Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l -- ^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v Hal Evans hgevans AT indiana.edu http://pages.iu.edu/~hgevans/ Tel: (812)856-3828 Fax: (812)855-5533 253 Swain Hall West Indiana University 727 E. Third St. Bloomington, IN 47405 v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^ | 
Attachment:
ScheduleFloat_NSF-DR.png
Description: PNG image
- 
            
            [Usatlas-hllhc-l2deputymgmt-nsf-l] contingency presentation sheet,
            Gustaaf Brooijmans, 07/19/2019
- 
            
            Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] contingency presentation	sheet,
            Gustaaf Brooijmans, 07/19/2019
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] contingency presentation sheet, Hal Evans, 07/19/2019
 
 
- 
            
            Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] contingency presentation	sheet,
            Gustaaf Brooijmans, 07/19/2019
Archive powered by MHonArc 2.6.24.