- Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] Next ICE steps
- Date: Thu, 1 Aug 2019 17:08:58 -0400
Hello all,
With the new documentation, MPR, the ACE subcontractor that performs the Independent Cost Estimate, was able to get some usable results. We will therefore continue with this model, and it is now time to finalize the new documentation packages for the other deliverables.
Attached is the ICE worksheet you completed. Please put together the new packages in docdb: *one "docdb document" per L3*, containing all the files needed for them to get quotes, ie everything listed in the spreadsheet, but NOT the TDRs. (We will add those on our side.) Please *name the docdb document "ICE Phase 2 6.x.y"* (with x and y the relevant numbers).
This is due by *COB next Friday, August 9*.
Thanks,
Gustaaf
Attachment:
ICE-large-procurements-sent20190715.xlsx
Description: application/vnd.openxmlformats-officedocument.spreadsheetml.sheet
- [Usatlas-hllhc-l2deputymgmt-nsf-l] Next ICE steps, Gustaaf Brooijmans, 08/01/2019
Archive powered by MHonArc 2.6.24.