Hello all,
Just to be clear, the questions with input needed from the L2s/system teams are:
1. if you haven't done so yet, please provide an earliest/latest decision point to Hal to update our table
3. Please provide an ordered table to me
4. Each L2, please send me and Hal the item you're most worried about, and we'll downselect
7. LAr to provide 1-2 slides
8. LAr and muon to provide a few sentences each
9. Mike, please provide a phrasing that's not too contradicting
10. Each L2 provide 2 slides: one with top 5 items, one with DD for one of them
11. Mark K: please provide a slide
Thanks,
Gustaaf
On 9/11/19 5:36 PM, Michael Tuts wrote:
Probably homework assignments are obvious…enjoy
*From:* Tony Beasley <tbeasley AT nrao.edu>
*Sent:* Wednesday, September 11, 2019 5:26 PM
*To:* Michael Tuts <tuts AT pmtuts.net>; Mark Coles (mcoles AT nsf.gov) <mcoles AT nsf.gov>
*Subject:* Homework - Day 1
Dear Mike,
Please find some questions from the Panel to be addressed at 8:30am tomorrow. Expect a short paragraph, verbal description or diagram in most cases.
thanks… Tony
1. Descope/upscope items - please provide both preferred/scheduled and
need-by dates...
2. Please provide a schedule of expiration of descope options
throughout project. please focus on dates...
3. Provide top 5 risks in rank order (worst->least) for each major
subsystem. The risk register is dense .. would like to see the major
concerns.
4. Hank Evans: please provide a rank-ordered list of remaining work
packages (in the pre-MREFC project) - what are you most concerned
about? Please mention your “plan B's”.
5. Please provide the total project BOE distribution - pie chart format.
6. Columbia mgt decision to implement 30 subawards generates a cost
impact ~$186k ... was this to support EV reporting? What did the
project gain from this change?
7. What risks are being carried forward by the project by the
(aggressive?) scheduled downselect of the ADC in December? e.g.
radiation tolerance of the ADC ASIC version 3? Please clarify
statement on radiation tolerance of commercial ADC option.
8. What is the schedule risk of the late delivery of the production
version of lpGBT?
9. Please restate/clarify Scientific travel – where is it covered in
the MREFC award? Suggest: please produce List of significant things
not in there yet.... don't let us find them.
10. For each subsystem - what are the (5) major technical requirements,
and what is your assessment of your ability to meet them (and what
is the basis of that assessment?). Please trace one major
science/technical specification from the international ATLAS
specification, through your US ATLAS specification set, indicate
where addressed in design, and demonstrate how you intend to assess
compliance.
11. Please describe the connections between the EPO manager, the L2
managers, and the EPO proponents at the partner universities. How is
communication/coordination occuring between these groups? How
specifically will the project take advantage of community
initiatives like QUARKNET? Give examples of joint activities being
considered.
12. How exposed is the US project to CERN Project Management
uncertainties in schedule? If CERN schedule drifts across many
subsystems, could the US project be negatively impacted beyond
current expectations?
///
_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l
--
Gustaaf Brooijmans - Columbia University
@Columbia: (212) 854 4527; Nevis virtual phone: (914) 591 2804
Als sie mich holten,
gab es keinen mehr, der protestieren konnte.
-
[Usatlas-hllhc-l2deputymgmt-nsf-l] FW: Homework - Day 1,
Michael Tuts, 09/11/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] [Usatlas-hllhc-management-l] FW: Homework - Day 1,
Gustaaf Brooijmans, 09/11/2019
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] [Usatlas-hllhc-management-l] FW: Homework - Day 1, George Redlinger, 09/11/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: Homework - Day 1,
Gustaaf Brooijmans, 09/11/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: Homework - Day 1,
John Parsons, 09/11/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: Homework - Day 1,
Elliot Lipeles, 09/11/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: Homework - Day 1,
Gustaaf Brooijmans, 09/11/2019
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] [External] Re: FW: Homework - Day 1, Hal Evans, 09/11/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: Homework - Day 1,
Gustaaf Brooijmans, 09/11/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: Homework - Day 1,
Thomas Schwarz, 09/11/2019
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: Homework - Day 1, John Parsons, 09/11/2019
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: Homework - Day 1, Elliot Lipeles, 09/11/2019
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: Homework - Day 1, Gustaaf Brooijmans, 09/11/2019
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: Homework - Day 1, Elliot Lipeles, 09/11/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: Homework - Day 1,
Thomas Schwarz, 09/11/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: Homework - Day 1,
Gustaaf Brooijmans, 09/11/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: Homework - Day 1,
Elliot Lipeles, 09/11/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: Homework - Day 1,
John Parsons, 09/11/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] [Usatlas-hllhc-management-l] FW: Homework - Day 1,
Gustaaf Brooijmans, 09/11/2019
Archive powered by MHonArc 2.6.24.