Hello all,

Where are all of you on the final "MREFC fixes" BCPs? Before we can start the MREFC we need all the fixes in (including the corrections for "overloaded" tasks) and we'll need to re-run fuse and send NSF the fuse report + an analysis.

Thanks,

Gustaaf