usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List
List archive
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] October variance reports
- From: John Parsons <parsons AT nevis.columbia.edu>
- To: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>, usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
- Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] October variance reports
- Date: Mon, 29 Nov 2021 13:43:08 -0500
Actually, as I sent you over the weekend, 6.4.2 is done.
On 11/29/21 12:53 PM, Gustaaf Brooijmans wrote:
Hello all,
Here's today's follow-up, please keep in mind the recommendation from the EVMS review:
"In VARs with multiple drivers, quantify the cost and schedule impacts with each identified driver, especially for VARs with both COVID and non-COVID related variances.* (Guideline 23)"
-6.4.1: [hasn't been updated] it's acceptable, but I have a hard time believing the board delay is $135k. That's many months of full-time work, incompatible with being back on track "next month:"
-6.4.2 is still missing
-6.4.3: [hasn't been updated] see above: how much is due to the french delay vs lack of parts?
-6.5: Good, thanks.
-6.5.1: Good, thanks.
-6.6: "the material costs were below budgeted cost" => this cannot contribute to a schedule variance, only a cost variance (but the tech part is fixed).
-6.6.1 is good, thanks
-6.6.3 is good, thanks
-6.6.4 is good, thanks
-6.6.5 is good, thanks
-6.8.2 is interesting, and ok in my view, but let's see what NSF says.
-6.8.3 is good
Best,
Gustaaf
On 11/24/21 12:44 PM, Gustaaf Brooijmans wrote:
Hello all,
Please remember that the monthly report needs to go to NSF early next week.
BTW, it's easy to quantify where the schedule variance is - that info can be read off the CPR easily when unrolling down to task level.
A quick follow-up:
-6.4.1: it's acceptable, but I have a hard time believing the board delay is $135k. That's many months of full-time work, incompatible with being back on track "next month:"
-6.4.2 is still missing
-6.4.3: [hasn't been updated] see above: how much is due to the french delay vs lack of parts?
-6.5: Good, thanks.
-6.5.1: Good, thanks.
-6.6: [hasn't been updated] "the material costs were below budgeted cost" => this cannot contribute to a schedule variance, only a cost variance; "The sMDT also has had a technician temporarily leave, so labor costs are reduced. " => idem
-6.6.1: [hasn't been updated] see above: please quantify the respective contributions of the two sources
-6.6.3: [hasn't been updated]so when will the pre-production submission happen? "Not just yet" is now 3 months...
-6.6.4: [hasn't been updated] even after taking into account preproduction there is still a $140k schedule variance, so this needs a bit more explanation...
-6.6.5: [hasn't been updated] see above: please quantify the respective contributions of the two sources; will the BCP have any impact on the schedule variance?
-6.8.2 is interesting, and ok in my view, but let's see what NSF says.
-6.8.3 is good
Enjoy the holidays!
Gustaaf
On 11/22/21 1:50 PM, Gustaaf Brooijmans wrote:
_______________________________________________
Hello L2 managers,
Thanks for filling many of the variance reports already. Please keep in mind the recommendation from the EVMS review:
"In VARs with multiple drivers, quantify the cost and schedule impacts with each identified driver, especially for VARs with both COVID and non-COVID related variances.* (Guideline 23)"
A few comments to send to the CAMs:
-6.4.1: how much of the $200k is in the board delays? Presumably not all, since it's a one month delay...
-6.4.2 is missing
-6.4.3: see above: how much is due to the french delay vs lack of parts?
-6.5: Why is shipping preproduction boards a corrective action?
-6.5.1: typo: was well as
-6.6: "the material costs were below budgeted cost" => this cannot contribute to a schedule variance, only a cost variance; "The sMDT also has had a technician temporarily leave, so labor costs are reduced. " => idem
-6.6.1: see above: please quantify the respective contributions of the two sources
-6.6.3: so when will the pre-production submission happen? "Not just yet" is now 3 months...
-6.6.4: so even after taking into account preproduction there is still a $140k schedule variance, so this needs a bit more explanation...
-6.6.5: see above: please quantify the respective contributions of the two sources; will the BCP have any impact on the schedule variance?
-6.8.2 is a copy paste from the previous month, but what is asked now is a report on the *positive cost variance*! This needs to be rewritten from scratch...
-6.8.3 is good
Thanks!
Gustaaf
_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l
--
______________________________________________________________________
John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW:
https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!W7KgMchBuYFzjFVTWR6YOQvDRmaCs6yu2rP-j7HFNT-Tvp2FbEbtBAcU9b6zgUPfG7pJwpfdPAx8j-BYzgv9wmCFQ-_W$
______________________________________________________________________
-
[Usatlas-hllhc-l2deputymgmt-nsf-l] October variance reports,
Gustaaf Brooijmans, 11/22/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] October variance reports,
Gustaaf Brooijmans, 11/24/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] October variance reports,
Gustaaf Brooijmans, 11/29/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] October variance reports,
John Parsons, 11/29/2021
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] October variance reports, Gustaaf Brooijmans, 11/29/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] October variance reports,
John Parsons, 11/29/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] October variance reports,
Gustaaf Brooijmans, 11/29/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] October variance reports,
Gustaaf Brooijmans, 11/24/2021
Archive powered by MHonArc 2.6.24.