[Usatlas-hllhc-l2deputymgmt-nsf-l] Questions for NSF COVID BCP schedule aspects
- From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
- To: Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
- Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] Questions for NSF COVID BCP schedule aspects
- Date: Wed, 2 Mar 2022 11:25:46 +0100
Hello Tom and Anyes,
We're filling out the NSF COVID BCP schedule form, so I’m looking at the
schedule diffs. I’m trying to understand some muon delay numbers:
*TDC delay of 233 days: the variance reports in the past 6 months said the
issues were largely technical, not COVID. So why is all this delay assigned
to COVID?
*CSM: there the variance reports did talk about COVID, but not just COVID,
so 211 days seems steep…
Thx
Gustaaf