Skip to Content.
Sympa Menu

usatlas-hllhc-l2deputymgmt-nsf-l - Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] June variance reports

usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List

List archive

Chronological Thread  
  • From: Thomas Schwarz <schwarzt AT umich.edu>
  • To: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • Cc: Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
  • Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] June variance reports
  • Date: Fri, 29 Jul 2022 08:48:14 -0400

This is done for muons.

Tom

===================
Tom Schwarz
Associate Professor
Department of Physics
University of Michigan 
Office: 734-764-8941
Lab: 734-763-7805
===================



On Fri, Jul 29, 2022 at 4:49 AM Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu> wrote:

Hello all,

-6.4.1 is still missing the SV
-6.4.3 reports on a schedule variance when it’s supposed to report on a cost variance!!  Can people please pay attention to what is actually asked?  It’s spelled out explicitly!

-6.6: I wonder if you shouldn’t plan on a BCP to delay CSM production - see below.
-6.6.3: still > $100k unexplained…
-6.6.4: shouldn’t you at least have a BCP to delay production if you already know pre-production is going to be a problem?

Please fix today.

Thx

Gustaaf

On Jul 28, 2022, at 5:11 PM, Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu> wrote:


Hello all,

A follow-up, please keep in mind that these need to be finalized tomorrow, so please make sure the issues below are all addressed *today*!

-6.4.1 is still missing the SV
-6.4.2 seems fine
-6.4.3 is still missing

-6.6 is still missing
-6.6.3: maybe the delay due to substrates can be quantified?
-6.6.4 is still missing the SV

Thanks,

Gustaaf


On Jul 26, 2022, at 7:38 PM, Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu> wrote:


Hello all,

Here are my comments on the June VRs.  Please make sure to get this done in the next few days.

Thx

Gustaaf

-6.4.1: thanks for the CV report, but the SV is missing
-6.4.2 is missing
-6.4.3 is missing

-6.6 is missing
-6.6.3: $110k in SV remains unexplained
-6.6.4 is missing the schedule variance explanation

-6.8* looks good
-6.10 looks fine

_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l


_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l



Archive powered by MHonArc 2.6.24.

Top of Page