Skip to Content.
Sympa Menu

usatlas-hllhc-l2deputymgmt-nsf-l - Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF Quarterly Risk Workshop (Preparation for NSF re-baseline review)

usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List

List archive

Chronological Thread  
  • From: "Meyer, Chris" <cjmey AT iu.edu>
  • To: "Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
  • Cc: "usatlas-hllhc-management-l AT lists.bnl.gov" <usatlas-hllhc-management-l AT lists.bnl.gov>
  • Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF Quarterly Risk Workshop (Preparation for NSF re-baseline review)
  • Date: Thu, 26 Jan 2023 18:37:54 +0000

Dear NSF L2s,

A friendly reminder of our NSF risk workshop next week (Tuesday, January 31) during the CCB meeting:

https://indico.bnl.gov/event/18087/

Cheers,
Chris

From: Meyer, Chris <cjmey AT iu.edu>
Sent: Thursday, January 12, 2023 10:48
To: Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
Cc: usatlas-hllhc-management-l AT lists.bnl.gov <usatlas-hllhc-management-l AT lists.bnl.gov>
Subject: Re: NSF Quarterly Risk Workshop (Preparation for NSF re-baseline review)
 
As promised, here is the preliminary agenda for the January 31 NSF risk workshop:

https://indico.bnl.gov/event/18087/

Cheers,
Chris

From: Meyer, Chris <cjmey AT iu.edu>
Sent: Thursday, January 12, 2023 10:30
To: Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
Cc: usatlas-hllhc-management-l AT lists.bnl.gov <usatlas-hllhc-management-l AT lists.bnl.gov>
Subject: NSF Quarterly Risk Workshop (Preparation for NSF re-baseline review)
 
Dear NSF L2s and Deputy L2s,

In preparation for the NSF re-baseline review, we will hold our quarterly NSF risk workshop during the CCB meeting on Tuesday, January 31. We will cover all systems in one meeting (~10 min per subsystem) and the agenda will be circulated soon.

As usual, please prepare slides covering:
  • Changes in risks since the last risk review (especially those that can be retired);
  • Updated task affected (to make sure it remains in the future);
  • In particular, if you list multiple tasks affected include a clear description of how to treat this in the simulation. I.e., the risk should hit both tasks listed simultaneously (rare), or a chain of tasks is listed as a reminder but only the first should be considered in the simulation;
Update comments to clearly describe how the cost/duration uncertainties are arrived at;Potential changes to risks before the upcoming review, e.g.:
  • changes to probability/impact of existing risks due to upcoming technical reviews;
  • existing risks that could be realized or that need to be watched carefully;
  • risks that might be retired.
The current risk register in docDB is v75, and the supply chain risk register is v7:


Please look over both in preparation for the workshop. After the workshop, please send Chris an updated version of the excel spreadsheet with your changes highlighted.

Any issues, please let us know.