[Usatlas-hllhc-l2deputymgmt-nsf-l] Summary of COVID BCP delays
- From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
- To: Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
- Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] Summary of COVID BCP delays
- Date: Fri, 17 Feb 2023 17:17:28 +0100
Hello NSF L2s,
I think I now have the COVID BCP delays right.  Here’s the table, let me know if there’s any disagreement with what you’re putting together.
Best,
Gustaaf
| BCP NSF-033  | BCP NSF-038 | BCP NSF-045 | BCP NSF-057a | Total | |
| LAr FEB2 | 82d | 126d | 108d | 33d | 349d | 
| LAr BEE HW | 134d | 47d | 143d | 0d | 324d | 
| LAr BEE FW | 119d | 95d | 142d | 0d | 356d | 
| Tile Main Board | 122d | 86d | 60d | 0d | 268d d | 
| Tile LVPS | 169d | 258d | 115d | 91d | 633d | 
| Muon sMDT | 104d | - | - | 199d | 303d | 
| Muon TDC | 64d | 64d | 82d | 22d | 232d | 
| Muon CSM | 171d | 23d | 219d | 125d | 538d | 
| Muon L0MDT | - | 60d | 37d | 44d | 141d | 
| Trigger GEP | 82d | 70d | 0d | 0d | 152d | 
- [Usatlas-hllhc-l2deputymgmt-nsf-l] Summary of COVID BCP delays, Gustaaf Brooijmans, 02/17/2023