Skip to Content.
Sympa Menu

usatlas-hllhc-l2deputymgmt-nsf-l - Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Milestone follow-up

usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List

List archive

Chronological Thread  
  • From: "Zhang, Jinlong" <zhangjl AT anl.gov>
  • To: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • Cc: "Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
  • Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Milestone follow-up
  • Date: Thu, 2 Mar 2023 17:56:53 +0000

Thanks a lot.

On Mar 2, 2023, at 11:55 AM, Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu> wrote:


Sorry, it’s red in the (now) attached sheet.  The red ones are copied over below.  None in Trigger, as it’s LAr BEE, Tile LVPS and Muon CSM.



On Mar 2, 2023, at 12:54 PM, Zhang, Jinlong <zhangjl AT anl.gov> wrote:

Sorry Gustaaf, I do not see red color somehow?

On Mar 2, 2023, at 11:49 AM, Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu> wrote:


Hello all,

Triggered by Victor’s question, I made a column of networkdays between FDR and current dates for the miletone table Penka produced.  It’s attached here, and there are in fact a few outliers (in red) for which we should have an explanation ready.

LAr:
BEE10795EX External Milestone: ATLAS PRR 3 2/3/23   5/22/25 600 350 COVID + 250??
BEE10920 Milestone: Lot 1 Production Complete 4 14-Feb-24   5/21/26 592
BEE11020 MS Tier 2 Physics Division: Lot 2 Production - End of Production 2 15-Jul-24   11/12/26 609


Tile:
LVP528000 MS Tier 2 Physics Division: Start - Production 2 1/26/21 2/6/24   791 633 COVID + 170 technical, ok?
LVP528210 MILESTONE: Production 50% Complete 4 4/26/22   5/23/25 804
LVP540370 MS Tier 2 Physics Division: 100% Production Complete 2 16-Feb-23   3/18/26 805

Muon:

CSM2635EX External Milestone: Production Readiness Review (PRR) 4 6-Nov-20   12/4/23 802 538 COVID + 250 technical?
CSM2790 MS Tier 2 Physics Division: Production Complete 2 22-Jun-22   7/17/25 802

Can you explain these?

Thx

Gustaaf
_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l


<Milestone Table NSF FDR 20190812 (1).xlsx>




Archive powered by MHonArc 2.6.24.

Top of Page