Skip to Content.
Sympa Menu

usatlas-hllhc-l2deputymgmt-nsf-l - [Usatlas-hllhc-l2deputymgmt-nsf-l] World events after rebaseline

usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List

List archive

Chronological Thread  
  • From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • To: Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
  • Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] World events after rebaseline
  • Date: Wed, 15 Mar 2023 14:07:41 +0100


Hello all,

Following some discussion, I think it’s important to be explicit about the
role of the “supply chain” risks going forward.

Per NSF policy, contingency can only be used to cover known risks. After
rebaseline, this will include any risks associated with “world events”.
Therefore I advise you to look at the supply chain risk register carefully:
once we are past baseline, if there is a “world events” instance that leads
to a significant cost increase or delay, and that instance was not captured
in the supply chain risk register, we will be forced to *descope* to address
it. (The global commodity volatility risk relates to tariffs and similar
issues, not the world events that are included in the rebaseline.)

So, please make sure you look at the risk register(s) carefully before the
review. We should not expect another bail-out! Also, we will now be held to
good SPI/CPI performance!