Skip to Content.
Sympa Menu

usatlas-hllhc-l2deputymgmt-nsf-l - Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF IPR contingency calculations

usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List

List archive

Chronological Thread  
  • From: "Schwienhorst, Reinhard" <schwier AT msu.edu>
  • To: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • Cc: "usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
  • Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF IPR contingency calculations
  • Date: Sat, 29 Jun 2024 14:31:12 +0000

Hi Gustaaf,
Here is the updated simulation for the contingency profile. This includes the risk change for LAr already. One comment: For Tile, there is a negative number in FY24 (likely because of the corrections that were made). I have left this as is for now, but I’d be happy to make adjustments if needed. Let me know if the updates make sense or if you see any issues.

Thanks,
Reinhard



On Jun 25, 2024, at 10:20 AM, Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu> wrote:


Hello all,

Attached is the summary of the contingency calculations.  We’re still double-checking a few things but with a little luck this will be final.

Best,

Reinhard & Gustaaf

_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://urldefense.com/v3/__https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l__;!!HXCxUKc!3wVQBEJS6MigvJHSkfmrPNz7ew2HQsy1EItcYzCp5fFjhLd--PNbDbict-rOuyIUHNlj0lysOCxwecTyu0PYLBQH$
<2024-07-nsf-ipr-public.xlsx>

Attachment: 2024-07-nsf-ipr-contingency-profile-v0.xlsx
Description: 2024-07-nsf-ipr-contingency-profile-v0.xlsx




Archive powered by MHonArc 2.6.24.

Top of Page