Hi all,
Apologies if you get this multiple times - I'm having some difficulties with my email....
Although I have not heard back from many of you on the updated scope contingency table that I circulated last week, we need to converge on a new version soon so that Mike can put it in his talk. To that end, I have collected what I have into a new version
of the spreadsheet, which is attached.
As backup - and so that we are all speaking the same language - I have included a few more details as to the justification for the changes in the google slide below:
https://docs.google.com/presentation/d/1IcRM2uHSVAyFMb94p189aKK5-j8zD36gk0jAn_9G2cE/edit?usp=sharing
There are a few remaining questions on the old scope contingency/opportunity items (for LAr, Muon, and Trigger). Please get back to me with any corrections to the spreadsheet/logic and answers to the questions below by Thursday so that we can get the updated
version of the spreadsheet posted by Friday.
Scope Contingency
- N-SC-6-04-02 (Reduce LAr BEE firmware effort): Remove?
- N-SC-6-08-004 (Reduce global algorithm firmware effort): Remove?
Scope Opportunity
- Is proposed priority ordering ok? The new elements are highest priority, by decision date.
- N-SO-6-06-001 (Purchase remaining L0MDT ATCA crate): Obsolete?
- N-SO-6-08-002 (Additional Global Algorithm): Move decision date Jan-24 -> May-25 (PRR)
- N-SO-6-08-003 (New Algorithm for L0Calo gFEX): Move decision date Jan-24 -> May-25
- N-SO-6-06-002 (Firmware for NSW Trigger Processor): Move decision date Oct-23 -> Oct-25
Thanks - Hal
--
------------------------------------------------------ Hal Evans hgevans AT iu.edu Professor of Physics http://hgevans.pages.iu.edu/ Tel: (812)856-3828 Fax: (812)855-5533 253 Swain Hall West Indiana University 727 E. Third St. Bloomington, IN 47405 ------------------------------------------------------
Attachment:
NSF-Scope-Contingency-Opportunity_v11.1.xlsx
Description: NSF-Scope-Contingency-Opportunity_v11.1.xlsx
-
[[Usatlas-hllhc-l2deputymgmt-nsf-l] ] Updated Scope Contingency,
Evans, Harold G., 07/09/2024
- <Possible follow-up(s)>
- [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] Updated Scope Contingency, Evans, Harold G., 07/09/2024
Archive powered by MHonArc 2.6.24.