Skip to Content.
Sympa Menu

usatlas-hllhc-l2deputymgmt-nsf-l - [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] August VRs

usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List

List archive

Chronological Thread  
  • From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • To: usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
  • Cc: Junjie Zhu <junjie AT umich.edu>, Thomas Schwarz <schwarzt AT umich.edu>, Haleh Hadavand <hadavand AT uta.edu>, Elliot Lipeles <lipeles AT sas.upenn.edu>
  • Subject: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] August VRs
  • Date: Fri, 20 Sep 2024 15:33:38 -0400


Hello all,

Thanks to those who have completed their VRs; others please do so asap.
Below are my comments so far.

Best,

Gustaaf

-6.4 and 6.4.2 are missing
-6.4.1 I have approved (although limited impact != no impact….)
-6.4.3 I have approved

-6.5.4 is missing

-6.6: I have approved, assuming more details on the CSM will be in the CSM VR
(see below)
-6.6.3 has a typo: “results in an overestimate” => "results from an
overestimate” I have unlocked because it drastically changes the meaning, so
needs to be fixed.
-6.6.4: in an email a week or so ago I asked to be more precise: by how much
has it slipped? When will it be cleared up? How much float is left? I have
unlocked so you can add that information
-6.6.5 I have approved

-6.8 and 6.8.4 are missing