  • From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • To: usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
  • Cc: Haleh Hadavand <hadavand AT uta.edu>
  • Subject: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] December VRs
  • Date: Tue, 21 Jan 2025 17:25:46 +0100


Hello all,

Thanks for filing your variance reports on time (Haleh, please do so asap).
Below are my comments.

Best,

Gustaaf

--

6.4: I have approved all. (As a side note on 6.4.3, it is true that the
fractional cost variance will go down, but not the amount in principle…)

6.6 there are extra words: "to align the US schedule to the with the actual “
=> I have unlocked this
6.6.3, 6.6.4 I have approved
6.6.5: There’s a word missing: "The completion of the v2 prototype and the
pre-production are delayed by 12. “ => I have unlocked this

6.8.1: we cannot have something like this in a VR: "No corrective actions are
needed at this time… UPDATE: Will now look at starting a BCP to…” => I have
unlocked this
6.8.4I have approved