Hello all,
Thanks for filing your variance reports on time (Haleh, please do so asap).
Below are my comments.
Best,
Gustaaf
--
6.4: I have approved all. (As a side note on 6.4.3, it is true that the
fractional cost variance will go down, but not the amount in principle…)
6.6 there are extra words: "to align the US schedule to the with the actual “
=> I have unlocked this
6.6.3, 6.6.4 I have approved
6.6.5: There’s a word missing: "The completion of the v2 prototype and the
pre-production are delayed by 12. “ => I have unlocked this
6.8.1: we cannot have something like this in a VR: "No corrective actions are
needed at this time… UPDATE: Will now look at starting a BCP to…” => I have
unlocked this
6.8.4I have approved
-
[[Usatlas-hllhc-l2deputymgmt-nsf-l] ] December VRs,
Gustaaf Brooijmans, 01/21/2025
-
[[Usatlas-hllhc-l2deputymgmt-nsf-l] ] December VRs for 6.5.4 and 6.8.1,
Gustaaf Brooijmans, 01/24/2025
- Re: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] December VRs for 6.5.4 and 6.8.1, Hayden, Daniel, 01/24/2025
-
[[Usatlas-hllhc-l2deputymgmt-nsf-l] ] December VRs for 6.5.4 and 6.8.1,
Gustaaf Brooijmans, 01/24/2025
Archive powered by MHonArc 2.6.24.