Skip to Content.
Sympa Menu

usatlas-hllhc-l2deputymgmt-nsf-l - [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] April VRs

usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List

List archive

Chronological Thread  
  • From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • To: usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
  • Cc: Haleh Hadavand <hadavand AT uta.edu>, "Schwienhorst, Reinhard" <schwier AT msu.edu>, Timothy Robert Andeen <timothy.robert.andeen AT cern.ch>, Elliot Lipeles <lipeles AT sas.upenn.edu>, "Hayden, Daniel" <haydend5 AT msu.edu>
  • Subject: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] April VRs
  • Date: Tue, 20 May 2025 16:41:10 +0200


Hello all,

Here are my comments on this month’s VRs.

Best,

Gustaaf

-6.4.1: I have approved, but if all VTRx+ have been received, why is there a
negative schedule variance.
-6.4.2 I have approved

-6.5.4 is missing

-6.6.1 is missing
-6.6.3 I have approved
-6.6.4 I will wait for confirmation that there was a typo - the point of VRs
is that we show we understand what’s going on…

-6.8.1 I have approved, but given the latest news from samtec, it seems a
little weird to say this has been “finalized”
-6.8.4 I have unlocked: you also owe a report on the SV.