Skip to Content.
Sympa Menu

usatlas-hllhc-l2deputymgmt-nsf-l - Re: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] Risk adjusted project end date?

usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List

List archive

Chronological Thread  
  • From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • To: Michael Tuts <tuts AT pmtuts.net>
  • Cc: Reinhard Schwienhorst <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
  • Subject: Re: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] Risk adjusted project end date?
  • Date: Fri, 27 Jun 2025 08:56:47 +0200


Hi Mike,

12/14/28 (LAr FEB2).  In the file you’ll see some later dates in the 90% CL column, but in those cases the schedule contingency task is included in the deterministic date.

Best,

Gustaaf


On Jun 27, 2025, at 01:48, Michael Tuts <tuts AT pmtuts.net> wrote:

Hi Gustaaf and Reinhard,
Can you tell me the new risk adjusted MREFC project end date. What I reported last year was May 10 2028. I need that date for my NSF talk.
Thanks, Mike