usatlas-hllhc-l2deputymgmt-nsf-l - Re: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] Muon slides in Doc DB #

usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List

List archive

Chronological Thread  
  • From: Anyes Taffard <anyes.taffard AT cern.ch>
  • To: "gusbroo AT nevis.columbia.edu" <gusbroo AT nevis.columbia.edu>
  • Cc: Anyes Taffard <anyes.taffard AT cern.ch>, "usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>, Rosemarie Smith <rsmith2 AT bnl.gov>
  • Subject: Re: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] Muon slides in Doc DB #
  • Date: Fri, 27 Jun 2025 20:24:37 +0000

Hi

Updated slides have been uploaded to docDB (and consequently the indico agenda).

Emailed P/J/T (cc you) regarding the CSM float calc.

Best,
-a

On Jun 27, 2025, at 10:47, Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu> wrote:


Hello Anyes,


-sl 11: external dependencies for 6.6.3…
It’s there - 1st line - ain’t any

“for” not “on"


-sl 17: what do you mean by “risk mitigation before launching pre-prod”?  Define MDTTP (or maybe better don’t use it, just say L0MDT)
The SM rev and CM prototype v2 have the FDR changes, so there are essentially test pre-production boards.

Changes between prototypes and preproduction are allowed of course.  Anyway, maybe say this rather than just “risk mitigation”? 



-sl 27: the 255/241 is for CSM, not L0MDT!!  (See the spreadsheet we sent.)  This may also invalidate your statement on the previous slide about main remaining risks…

I don’t quite understand why we now have 255 wd float for CSM
Last year we had 6 days
We added ~1 yr to account for LS3 date change but we lost 1 yr in pre-production. 

Last year CSM needed 239 and had 11.  I also don’t know how the CSM available float is calculated because I see no need-by date.  I lifted the 255 from the schedule file I downloaded from IPD.  There I see:

<Screenshot 2025-06-27 at 19.43.51.png>

And the same is shown in the schedules posted for the review.

Maybe ask the CAM?


Last year the float was computed between these 2 tasks below and we had 11 WD float.
- CSM WS (CSM2790 ) ends on Dec 15 2025
- And CSM2810EX Jan 2 2026

As of May 2025:  
- CSM WS (CSM2790 ) ends on June 19 2026
- And CSM2810EX June 19 2026.

According to ATLAS schedule
- MDT Elx for endcap require June 3rd 2026
- MDT Elx for BIL required Nov 2nd 2026
- The Endcap installation starts on mid July 2026

So unless you change the dates on how the float is calculated I don’t understand why this number is now so large.
In the backup p60, I have the detail plans for production batch delivery. 

For L0MDT, the 289 wd come from L0MDT5460

Yes, so maybe take that.  L0MDT finishes after CSM anyway.

Best,

Gustaaf




-sl 34: deliverable*s* leverage; the 241 is for CSM, see above; progress has been made
Done

Best,
-a

Best,

Gustaaf

On Jun 26, 2025, at 08:18, Anyes Taffard (via usatlas-hllhc-l2deputymgmt-nsf-l Mailing List) <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov> wrote:

Hi all,

The Muon L2 slides are posted in Doc DB #1892 and linked to the indico agenda.

Best,
Anyes