Re: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] Muon slides in Doc DB #
- From: Anyes Taffard <anyes.taffard AT cern.ch>
- To: "gusbroo AT nevis.columbia.edu" <gusbroo AT nevis.columbia.edu>
- Cc: Anyes Taffard <anyes.taffard AT cern.ch>, "usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>, Rosemarie Smith <rsmith2 AT bnl.gov>
- Subject: Re: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] Muon slides in Doc DB #
- Date: Fri, 27 Jun 2025 20:24:37 +0000
Hi
Updated slides have been uploaded to docDB (and consequently the indico agenda).
Emailed P/J/T (cc you) regarding the CSM float calc.
Best,
-a
On Jun 27, 2025, at 10:47, Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu> wrote:
Hello Anyes,
It’s there - 1st line - ain’t any-sl 11: external dependencies for 6.6.3…
“for” not “on"
The SM rev and CM prototype v2 have the FDR changes, so there are essentially test pre-production boards.-sl 17: what do you mean by “risk mitigation before launching pre-prod”? Define MDTTP (or maybe better don’t use it, just say L0MDT)
Changes between prototypes and preproduction are allowed of course. Anyway, maybe say this rather than just “risk mitigation”?
-sl 27: the 255/241 is for CSM, not L0MDT!! (See the spreadsheet we sent.) This may also invalidate your statement on the previous slide about main remaining risks…
I don’t quite understand why we now have 255 wd float for CSMLast year we had 6 daysWe added ~1 yr to account for LS3 date change but we lost 1 yr in pre-production.
Last year CSM needed 239 and had 11. I also don’t know how the CSM available float is calculated because I see no need-by date. I lifted the 255 from the schedule file I downloaded from IPD. There I see:
<Screenshot 2025-06-27 at 19.43.51.png>
And the same is shown in the schedules posted for the review.
Maybe ask the CAM?
Last year the float was computed between these 2 tasks below and we had 11 WD float.- CSM WS (CSM2790 ) ends on Dec 15 2025- And CSM2810EX Jan 2 2026
As of May 2025:- CSM WS (CSM2790 ) ends on June 19 2026- And CSM2810EX June 19 2026.
According to ATLAS schedule- MDT Elx for endcap require June 3rd 2026- MDT Elx for BIL required Nov 2nd 2026- The Endcap installation starts on mid July 2026
So unless you change the dates on how the float is calculated I don’t understand why this number is now so large.In the backup p60, I have the detail plans for production batch delivery.
For L0MDT, the 289 wd come from L0MDT5460
Yes, so maybe take that. L0MDT finishes after CSM anyway.
Best,
Gustaaf
Done-sl 34: deliverable*s* leverage; the 241 is for CSM, see above; progress has been made
Best,-a
Best,
Gustaaf
On Jun 26, 2025, at 08:18, Anyes Taffard (via usatlas-hllhc-l2deputymgmt-nsf-l Mailing List) <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov> wrote:
-
[[Usatlas-hllhc-l2deputymgmt-nsf-l] ] Muon slides in Doc DB #,
Anyes Taffard, 06/26/2025
-
Re: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] Muon slides in Doc DB #,
Gustaaf Brooijmans, 06/27/2025
-
Re: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] Muon slides in Doc DB #,
Anyes Taffard, 06/27/2025
-
Re: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] Muon slides in Doc DB #,
Gustaaf Brooijmans, 06/27/2025
- Re: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] Muon slides in Doc DB #, Anyes Taffard, 06/27/2025
-
Re: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] Muon slides in Doc DB #,
Gustaaf Brooijmans, 06/27/2025
-
Re: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] Muon slides in Doc DB #,
Anyes Taffard, 06/27/2025
-
Re: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] Muon slides in Doc DB #,
Gustaaf Brooijmans, 06/27/2025