Skip to Content.
Sympa Menu

usatlas-hllhc-l2deputymgmt-nsf-l - [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] October VRs

usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List

List archive

Chronological Thread  
  • From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • To: usatlas-hllhc-l2deputymgmt-nsf-l <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
  • Cc: Amy Garwood <agarwood AT nevis.columbia.edu>, Andy Haas <andy.haas AT nyu.edu>, Haleh Hadavand <hadavand AT uta.edu>, Junjie Zhu <junjie AT umich.edu>
  • Subject: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] October VRs
  • Date: Sun, 23 Nov 2025 17:36:23 -0500

Hello all, Here are my comments on the October VRs: -6. 4 I have approved -6. 4. 1 I have approved -6. 4. 2 is problematic: I realize that we get costs directly from the Columbia system for Columbia L3s, but the PEP says we use accruals. So writing
ZjQcmQRYFpfptBannerStart
This Message Is From an External Sender
This message came from outside your organization.
 
ZjQcmQRYFpfptBannerEnd

Hello all,

Here are my comments on the October VRs:

-6.4 I have approved
-6.4.1 I have approved
-6.4.2 is problematic: I realize that we get costs directly from the Columbia system for Columbia L3s, but the PEP says we use accruals.  So writing a VR that directly contradicts the PEP is an issue.  For these large procurements we should really do accruals (we did this by hand for 6.9 so why not for 6.4?)  I guess it’s too late for this month, but maybe you should just write that the accrual for these items was not done?  I’ve unlocked this.
-6.4.3: you keep saying that a priming request has been submitted, but it has also been sent back/rejected.  It’s not wrong, so I have approved, but it is misleading, so please don’t do this in November.

-6.5.4: I have approved, but next month please say something in the impact about how much float is left. 

-6.6.3 is fine but needs to be submitted
-6.6.4 I have approved

-6.8.1 I have approved
-6.8.2 I have approved

Best,

Gustaaf