Skip to Content.
Sympa Menu

usatlas-hllhc-l2deputymgmt-nsf-l - [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] NSF risk worhshop Feb 24

usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List

List archive

Chronological Thread  
  • From: Reinhard Schwienhorst <reinhard.schwienhorst AT cern.ch>
  • To: "usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
  • Cc: "usatlas-hllhc-management-l AT lists.bnl.gov" <usatlas-hllhc-management-l AT lists.bnl.gov>
  • Subject: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] NSF risk worhshop Feb 24
  • Date: Sat, 24 Jan 2026 16:25:07 +0000

Dear NSF L2s and Deputy L2s, We would like to schedule the next NSF risk workshop for Tuesday, February 24 during the CCB meeting. In preparation, please prepare slides that focus on: - Risks that can now be retired. - New risks that might have
ZjQcmQRYFpfptBannerStart
This Message Is From an External Sender
This message came from outside your organization.
 
ZjQcmQRYFpfptBannerEnd
Dear NSF L2s and Deputy L2s,

We would like to schedule the next NSF risk workshop for Tuesday, February 24 during the CCB meeting. 
In preparation, please prepare slides that focus on:
- Risks that can now be retired.
- New risks that might have come up over the past 6 months, or issues that are worrying you these days.
- Large changes in probability or cost/duration uncertainty.
- Updating the task affected so that all tasks associated with risks are in the future. 
The current risk register in docDB (#196) is v98, and the supply chain risk register is v16:
https://atlas-hllhc.docdb.bnl.gov/0001/000196/119/Risk-Register_v98.xlsx
https://atlas-hllhc.docdb.bnl.gov/0001/000196/119/Risk-Register_Supply-Chain_v22.xlsx

Please look over both for this review. In addition to your slides, please also prepare updated versions of these registers with updated cells highlighted.

Any issues, please let me know.
Reinhard, on behalf of your friendly PO


  • [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] NSF risk worhshop Feb 24, Reinhard Schwienhorst, 01/24/2026

Archive powered by MHonArc 2.6.24.

Top of Page