[Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Cost/Schedule Performance reports
- From: John Parsons <parsons AT nevis.columbia.edu>
- To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
- Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Cost/Schedule Performance reports
- Date: Mon, 26 Nov 2018 15:12:38 -0500
-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2l3ics-l] Cost/Schedule Performance reports
Date: Tue, 20 Nov 2018 14:07:41 +0000
From: Novakova, Penka N <penka AT bnl.gov>
To: usatlas-hllhc-l2l3ics-l AT lists.bnl.gov <usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>
CC: Amy Garwood <agarwood AT nevis.columbia.edu>
System Managers,
We have completed the cost/schedule performance reports (CPRs) for the period beginning of project to the end of September 2018. The reports have been posted in docdb 624.
Please review the report for your system. When you analyze the data keep in mind
1. The results should be analyzed only as cumulative, the current
period is not meaningful at this point. The reason for this is that
the schedules have been statussed for many periods (months).
2. The actuals for FY17 and FY18 are uploaded at level 3 – e.g.
6.01.99, 6.02.99. We have not collected all the actuals data at a
lower level. Therefore the COST performance can be evaluated only at
Level 2.
3. For the schedule status (Schedule variance (SV) and Schedule
Performance Index (SPI) – columns J and L) you can click on the plus
sign at level 3 to expand the field and to see how each activity
affects the schedule performance. Remember that SV= Work Performed
(column H) - Work Budgeted (column G)
Please let us know if you have any questions or need help in interpreting the data. This is a standard reporting format that will be provided to you on a monthly basis and it is very important that you understand the data.
We plan to send the status spreadsheets for October/November next Monday, November 26.
Regards,
Penka on behalf of the project management team
_______________________________________________
Usatlas-hllhc-l2l3ics-l mailing list
Usatlas-hllhc-l2l3ics-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2l3ics-l
- [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Cost/Schedule Performance reports, John Parsons, 11/26/2018