[Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] Attending the kickoff meeting with the Army Corps of Engineers
- From: John Parsons <parsons AT nevis.columbia.edu>
- To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
- Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] Attending the kickoff meeting with the Army Corps of Engineers
- Date: Thu, 21 Mar 2019 17:58:27 -0300
-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] Attending the kickoff meeting with the Army Corps of Engineers
Date: Thu, 21 Mar 2019 18:51:45 +0000
From: Michael Tuts <tuts AT pmtuts.net>
To: Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov <Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
CC: usatlas-hllhc-pomgmt-l AT lists.bnl.gov <usatlas-hllhc-pomgmt-l AT lists.bnl.gov>
Hi NSF L2’s,
Please pass this on to your L3s. As I believe you are aware of, the NSF Independent Cost Estimate (ICE) has been contracted to the Army Corps of Engineers (who in turn subcontract to their ‘subject experts’). The ICE committee will likely consist of ~two Army Corps people plus two subject matter experts that they contract to. That process is starting and will consist of two phases.
* Phase 1 (used by NSF to evaluate the competency of the Army Corps
process): will focus on the pre-PDR subsystems (Muon TDC and LAr
ADC). They will only review only the material costs and not labor.
o Kickoff meeting with ICE scheduled for *April 9, 12-2pm
(eastern)* – see Webex contact info below.
o The documentation we have provided to them is available at DocDB
#655. The documents cover what NSF asked us for. Note that some
of the documentation intended for ICE is redacted to remove
material costs.
o Next week the Army Corps will review the documentation we sent
them and generate questions by April 1-2, that NSF will
distribute those question to us in advance of the kickoff
meeting on April 9.
* Phase 2: will cover the rest of the NSF scope
o Currently scheduled to begin ~mid-May
o Documentation needs to be ready by that time. You need to
prepare that information for your subsystem
* Although the Phase 1 focus is on the two pre-FDR systems, *all L2s
and L3s are invited to listen in on the April 9 meeting to
understand what will be needed by mid-May*.
Cheers, PO
Connection information for Army Corps kickoff meeting on April 9 12-2pm (eastern)
Below is the webex info:
https://usace.webex.com/join/simon.fet
Toll free: 866-434-5269
Long dist: 216-706-7005
Access Code: 4146923
Security Code: 4657
_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l
- [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] Attending the kickoff meeting with the Army Corps of Engineers, John Parsons, 03/21/2019
Archive powered by MHonArc 2.6.24.