usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List
List archive
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: RE: March 2019 HL-LHC ATLAS Detector Upgrade Monthly Report
- From: "Ma, Hong" <hma AT bnl.gov>
- To: "Parsons, John" <parsons AT nevis.columbia.edu>, "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
- Subject: Re: [Usatlas-hllhc-lartl2l3-l] Fwd: RE: March 2019 HL-LHC ATLAS Detector Upgrade Monthly Report
- Date: Fri, 22 Mar 2019 11:41:06 +0000
Dear John,
Here is a summary of PA/Shaper:
100 ALFEv0 dies arrived last weekend at BNL, and 55 were sent out for packaging on Monday. We expect them to be back March 26. The test PCB will be back from assembly next week, and testing will begin during the week of April 1. In parallel, there will be wirebonding at Instrumentation, which will allow testing to start sometime next week (March 28).
LAUROC1 is being tested in France, and we expect to receive the ASIC and test board at the Paris meeting early April.
Hong.
From:
Usatlas-hllhc-lartl2l3-l <usatlas-hllhc-lartl2l3-l-bounces AT lists.bnl.gov> on behalf of John Parsons <parsons AT nevis.columbia.edu>
I need to file the new monthly report, so email me any news from your L3. Please do so right away, since the report is due tomorrow.
Thanks, John
-------- Forwarded Message -------- Subject: RE: March 2019 HL-LHC ATLAS Detector Upgrade Monthly Report Date: Thu, 21 Mar 2019 22:44:21 +0000 From: Freedman, Rhoumela <rfreedman AT bnl.gov> To: Grenier, Philippe <grenier AT slac.stanford.edu>, ecanderssen AT lbl.gov <ecanderssen AT lbl.gov>, Parsons, John <parsons AT nevis.columbia.edu>, Schwarz, Thomas <schwarzt AT umich.edu>, Lipeles, Elliot <lipeles AT hep.upenn.edu>, lipeles AT cern.ch <lipeles AT cern.ch>, 'Tae Min Hong' <tmhong AT cern.ch> CC: Kotcher, Jonathan <kotcher AT bnl.gov>, 'Gustaaf Brooijmans' <gusbroo AT nevis.columbia.edu>, 'Hal Evans' <hgevans AT indiana.edu>, Butehorn, Charles J <butehorn AT bnl.gov>, 'Michael Tuts' <tuts AT pmtuts.net>, Novakova, Penka N <penka AT bnl.gov>
Hello everyone!
Just a reminder to please send your March Report by the end of the day tomorrow, March 22.
Thank you,
Rhoumela
*From:* Freedman, Rhoumela *Sent:* Friday, March 15, 2019 9:28 AM *To:* Grenier, Philippe <grenier AT slac.stanford.edu>; 'Carl Haber' <chhaber AT lbl.gov>; ecanderssen AT lbl.gov; Parsons, John <parsons AT nevis.columbia.edu>; oreglia AT uchicago.edu; Schwarz, Thomas <schwarzt AT umich.edu>; 'Zhang, Jinlong' <zhangjl AT anl.gov>; 'Elliot Lipeles <lipeles AT hep.upenn.edu>; lipeles AT cern.ch; 'Tae Min Hong' *Cc:* Kotcher, Jonathan <kotcher AT bnl.gov>; 'Gustaaf Brooijmans' <gusbroo AT nevis.columbia.edu>; 'Hal Evans' <hgevans AT indiana.edu>; Butehorn, Charles J <butehorn AT bnl.gov>; 'Michael Tuts' <tuts AT pmtuts.net>; Novakova, Penka N <penka AT bnl.gov> *Subject:* March 2019 HL-LHC ATLAS Detector Upgrade Monthly Report
Hello!
Please send the March report as soon as possible, but no later than Friday, March 22. My email address is rfreedman AT bnl.gov
Thank you,
Rhoumela
Rhoumela Freedman, Administrator
U.S. ATLAS HL-LHC Upgrade Project
Brookhaven National Laboratory, Physics Dept.
Tel: (631) 344-3460
Fax: (631) 344-6179
_______________________________________________ Usatlas-hllhc-lartl2l3-l mailing list
|
-
[Usatlas-hllhc-lartl2l3-l] Fwd: RE: March 2019 HL-LHC ATLAS Detector Upgrade Monthly Report,
John Parsons, 03/21/2019
- Re: [Usatlas-hllhc-lartl2l3-l] Fwd: RE: March 2019 HL-LHC ATLAS Detector Upgrade Monthly Report, Ma, Hong, 03/22/2019
Archive powered by MHonArc 2.6.24.