usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List
List archive
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-doe-l] QA/QC documents
- From: "Ma, Hong" <hma AT bnl.gov>
- To: "Parsons, John" <parsons AT nevis.columbia.edu>, "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
- Subject: Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-doe-l] QA/QC documents
- Date: Sun, 7 Apr 2019 01:50:33 +0000
Here is the draft QA/QC doc for PA/Shaper. Please comment.
Hong.
From: Usatlas-hllhc-lartl2l3-l <usatlas-hllhc-lartl2l3-l-bounces AT lists.bnl.gov> on behalf of John Parsons <parsons AT nevis.columbia.edu>
Sent: Friday, March 29, 2019 2:32 PM
To: usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-doe-l] QA/QC documents
Sent: Friday, March 29, 2019 2:32 PM
To: usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-doe-l] QA/QC documents
-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2deputymgmt-doe-l] QA/QC documents
Date: Fri, 29 Mar 2019 14:11:16 -0400
From: Hal Evans <hgevans AT indiana.edu>
To: Usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov
Dear DOE L2 Managers,
We need to prepare draft QA/QC documents for the upcoming Director's
Review. We will create one such document for each deliverable (or for
each L4 item if a deliverable consists of several independent items). At
this stage in the project, these documents will be quite brief (1-2
pages) and won't yet contain a lot of specific detail. They should
indicate though that we're thinking appropriately about integrating the
Quality Assurance and Quality Control processes into our project
planning and execution. These will be fleshed out as we move forward,
and especially toward a baseline.
Please ask your L3s (or L4s) to produce drafts of these documents to be
discussed during Upgrade Week. Aim to have first versions for discussion
ready by *Tuesday, April 9*.
Examples of documents, which also provide a template for use in your
systems can be found in the docdb:
- LAr FE Electronics:
https://atlas-hllhc.docdb.bnl.gov/cgi-bin/public/ShowDocument?docid=640
- Tile Main Board: (attached)
user=review ; pwd=p2-lhc
For those interested, background information can be found in:
- Quality Assurance Plan:
https://atlas-hllhc.docdb.bnl.gov/cgi-bin/public/ShowDocument?docid=5
- DOE QA Guide:
https://atlas-hllhc.docdb.bnl.gov/cgi-bin/public/ShowDocument?docid=414
Thanks - the PM Team
--
^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v
Hal Evans hgevans AT indiana.edu
http://pages.iu.edu/~hgevans/
Tel: (812)856-3828 Fax: (812)855-5533
253 Swain Hall West Indiana University
727 E. Third St. Bloomington, IN 47405
v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^
Attachment:
QAQC-6.4.5.v1.docx
Description: QAQC-6.4.5.v1.docx
- Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-doe-l] QA/QC documents, Ma, Hong, 04/06/2019