[Usatlas-hllhc-lartl2l3-l] Fwd: simulated LAr (DOE) completion dates (w/o NSF smearing)
- From: John Parsons <parsons AT nevis.columbia.edu>
- To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
- Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: simulated LAr (DOE) completion dates (w/o NSF smearing)
- Date: Tue, 14 May 2019 13:53:29 -0400
-------- Forwarded Message --------
Subject: simulated LAr (DOE) completion dates (w/o NSF smearing)
Date: Fri, 10 May 2019 00:52:53 +0000
From: George Redlinger <redlinger AT bnl.gov>
Reply-To: redlinger AT bnl.gov
To: Parsons, John <parsons AT nevis.columbia.edu>, Ma, Hong <hma AT bnl.gov>
CC: usatlas-hllhc-management-l AT lists.bnl.gov <usatlas-hllhc-management-l AT lists.bnl.gov>
Hi John, Hong, All,
I did the little study of simulating the full LAr schedule with risk+maturity turned on for the DOE part but turned off for the NSF part, i.e. the NSF part of the schedule just follows the baseline.
These are the results I get for the schedule delay (at 90% CL):
risk+maturity (DOE&NSF)
risk+maturity (DOE only)
6.4.4.1 FEB2 integration BNL
366 working days
226 working days
6.4.4.2 System Integration BNL
252 working days
111 working days
6.4.5.1 PA Shaper BNL
241 working days
242 working days
6.4.5.2 PA Shaper Penn
1 working day
1 working day
The DOE-smearing-only results seem to agree pretty well with what we showed at CD1.
- George