Skip to Content.
Sympa Menu

usatlas-hllhc-lartl2l3-l - [Usatlas-hllhc-lartl2l3-l] Fwd: RE: [Usatlas-hllhc-l2deputymgmt-nsf-l] Fwd: NSF FDR Director's Review Templates

usatlas-hllhc-lartl2l3-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List

List archive

Chronological Thread  
  • From: John Parsons <parsons AT nevis.columbia.edu>
  • To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
  • Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: RE: [Usatlas-hllhc-l2deputymgmt-nsf-l] Fwd: NSF FDR Director's Review Templates
  • Date: Thu, 18 Jul 2019 11:44:32 -0400




-------- Forwarded Message --------
Subject: RE: [Usatlas-hllhc-l2deputymgmt-nsf-l] Fwd: NSF FDR Director's Review Templates
Date: Thu, 18 Jul 2019 14:57:39 +0000
From: Novakova, Penka N <penka AT bnl.gov>
To: Parsons, John <parsons AT nevis.columbia.edu>, Ma, Hong <hma AT bnl.gov>
CC: Hal Evans (hgevans AT indiana.edu) <hgevans AT indiana.edu>, Gustaaf Brooijmans (gusbroo AT nevis.columbia.edu) <gusbroo AT nevis.columbia.edu>, Michael Tuts <tuts AT pmtuts.net>, Kotcher, Jonathan <kotcher AT bnl.gov>, Freedman, Rhoumela <rfreedman AT bnl.gov>

Attached is the milestone spreadsheet, it's by L2 WBS, I have posted this into docdb 665.

-----Original Message-----
From: John Parsons <parsons AT nevis.columbia.edu> Sent: Thursday, July 18, 2019 10:23 AM
To: Novakova, Penka N <penka AT bnl.gov>; Hal Evans <hgevans AT indiana.edu>; Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Fwd: NSF FDR Director's Review Templates


Hi Penka,

Thanks for the clarification on the pie charts. I do think a table of milestones (should we include the tier info. with it?) would be better than the Gantt charts, so it would be great if that could be made.
Thanks,
John

On 7/18/19 10:17 AM, Novakova, Penka N wrote:
John,
I will make a spreadsheet with the milestones and will send it to you to use
it as you wish.
Regarding the pie charts - we only show the estimation type which is based on
the maturity scores. If you go to the tabs Estimating Method and Estimating
Rules you can see how the maturity scores are translated to the estimation
type.
Let me know if you have any questions.
Thanks,
penka


-----Original Message-----
From: John Parsons <parsons AT nevis.columbia.edu>
Sent: Thursday, July 18, 2019 9:58 AM
To: Hal Evans <hgevans AT indiana.edu>; Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov; Novakova, Penka N <penka AT bnl.gov>
Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Fwd: NSF FDR Director's Review Templates


Hi Hal/Penka,

A couple questions on the graphics (I keep the list in cc. since it
might also be of interest for others):

- the milestone Gantt charts are essentially unreadable.
Is that we are supposed to use as graphics on the Milestone slides (We used to have tables of them that would be more readable?)

- for uncertainty, we do not find update pie charts of the various maturity categories for material(M1, M2, ...) and labor. Are we supposed to have those? All we have is a pie chart of Estimation Method (Analogy, ...), but that shows something different

Regards,
John

On 6/25/19 8:58 AM, Hal Evans wrote:
Hi again,

Apologies: I forgot to mention that the pwd for the CERNBox folder is:
    US-Atlas-2019

Hal



-------- Forwarded Message --------
Subject: NSF FDR Director's Review Templates
Date: Tue, 25 Jun 2019 08:13:14 -0400
From: Hal Evans <hgevans AT indiana.edu>
To: Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov



Dear L2Ms/DL2Ms,

We in the PO have prepared L2 and L3 talk templates and background information for the NSF FDR Director's Review. You can find this information on CERNBox. Please distribute to your L3s.
https://cernbox.cern.ch/index.php/s/Y25Sh5qQUxS0s6P

In the folder above, the files are:
    2019-06-14-FDR-requirements: summary of FDR requirements from the Major Facilities Guide
    HL-LHC FDR Charge...: the charge with notes indicating who should address each point
    NSF-Agenda: a possible agenda for the review
    NSF-Background-Material: some useful definitions
    NSF-L2-Template: L2 talk template (please use in preparing your
talk)
    NSF-L3-Template: L3 talk template (please use in preparing the L3
talks)

As the NSF ideas about this review are evolving, the above material may change, but it should provide a place to get started.

Please distribute the Review Preparation Timeline to your L3s as well.
https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_
s preadsheets_d_1-2DqnFxgpH6TxIhPUpG58zh2b3cDd-2DoA6TJyVCIS3bum8_edit-3
F usp-3Dsharing&d=DwIDaQ&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&
r =UENrYTOIs8Bh1NYw40_P-g&m=Ygy1xESyzNeefnFNnT-ggbp8R5BFambf2sBLeA6JWPc
& s=U9TamryAGXQlathzzQeQg-5lDLJj6wogxp-TkfQmpTM&e=

Do not hesitate to contact us if you have any questions or comments about the material above, and encourage your L3s to do the same.

Thanks  -  Hal (for the PO)

--
^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v
Hal Evanshgevans AT indiana.edu

https://urldefense.proofpoint.com/v2/url?u=http-3A__pages.iu.edu_-7Ehgevans_&d=DwIDaQ&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=UENrYTOIs8Bh1NYw40_P-g&m=Ygy1xESyzNeefnFNnT-ggbp8R5BFambf2sBLeA6JWPc&s=PJCu6n8kDb2XnTGg6gDOEw3XYu1viGDkavhg1QjPfQw&e=
Tel: (812)856-3828 Fax: (812)855-5533
253 Swain Hall West Indiana University
727 E. Third St. Bloomington, IN 47405
v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^

--
^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v
Hal Evanshgevans AT indiana.edu

https://urldefense.proofpoint.com/v2/url?u=http-3A__pages.iu.edu_-7Ehgevans_&d=DwIDaQ&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=UENrYTOIs8Bh1NYw40_P-g&m=Ygy1xESyzNeefnFNnT-ggbp8R5BFambf2sBLeA6JWPc&s=PJCu6n8kDb2XnTGg6gDOEw3XYu1viGDkavhg1QjPfQw&e=
Tel: (812)856-3828 Fax: (812)855-5533
253 Swain Hall West Indiana University
727 E. Third St. Bloomington, IN 47405
v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^


_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf
-
l


--
______________________________________________________________________

John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW:
https://urldefense.proofpoint.com/v2/url?u=http-3A__www.nevis.columbia.edu_-7Eparsons_&d=DwIDaQ&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=UENrYTOIs8Bh1NYw40_P-g&m=Ygy1xESyzNeefnFNnT-ggbp8R5BFambf2sBLeA6JWPc&s=-xrAZ7hg-Mbl75kq9B4nicx4GC_Tz0uV_ZSuBU492hQ&e=


______________________________________________________________________


--
______________________________________________________________________

John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW: https://urldefense.proofpoint.com/v2/url?u=http-3A__www.nevis.columbia.edu_-7Eparsons_&d=DwIDaQ&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=UENrYTOIs8Bh1NYw40_P-g&m=d3YZZ00nuyp63f7XlhSQjIQcUyHTgBK_U9ifSn1yK2E&s=evRVNSR4GB94wrKNhzrnNh3K771zbgLjoz_zOTxMeNw&e=

______________________________________________________________________

Attachment: Milestone Table DR FDR 20190718.xlsx
Description: application/vnd.openxmlformats-officedocument.spreadsheetml.sheet