Hi all,
The DOE risk scrubbing for LAr fell off the
radar. With the next 2 weeks being busy with AUW + LAr weeks,
I would propose holding the scrubbing on Tues. Nov. 26
using the regular LAr weekly meeting timeslot of
11 am NY time. Let me know if that works.
Regards,
John
--
______________________________________________________________________
John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW:
https://urldefense.proofpoint.com/v2/url?u=http-3A__www.nevis.columbia.edu_-7Eparsons_&d=DwICaQ&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=3_4aEa6xD2llgduTWuV1oxbF5pvOW2FF74rkg4Ao0Wk&s=QMZlWF116G9_PLARfLPHBhz3IqjTDBD-Hzi0VoLOt6Y&e=
______________________________________________________________________
-
[Usatlas-hllhc-lartl2l3-l] LAr DOE risk scrubbing,
John Parsons, 11/05/2019
- Re: [Usatlas-hllhc-lartl2l3-l] [Usatlas-hllhc-management-l] LAr DOE risk scrubbing, Gustaaf Brooijmans, 11/06/2019
Archive powered by MHonArc 2.6.24.