Re: [Usatlas-hllhc-lartl2l3-l] Fwd: Re: [Usatlas-hllhc-l2l3ics-l] November Status Sheets
- From: Tim Andeen <timothy.robert.andeen AT cern.ch>
- To: John Parsons <parsons AT nevis.columbia.edu>
- Cc: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
- Subject: Re: [Usatlas-hllhc-lartl2l3-l] Fwd: Re: [Usatlas-hllhc-l2l3ics-l] November Status Sheets
- Date: Sun, 24 Nov 2019 20:15:43 +0100
Hi John, Thanks for noticing. I think that mistake was introduced in a pervious version. I removed it (set % complete to 0) and put an expected finish date. I hope that doesn't make trouble in removing work that I said was complete a month ago (or more). Best, Tim
On Sat, Nov 23, 2019 at 6:24 PM John Parsons <parsons AT nevis.columbia.edu> wrote:
Hi Tim,
Thanks. Please check line 308 (lpGBT Engineering Chip Fab. +
Packaging), which you have indicated as complete for some reason.
John
On 11/22/19 5:54 PM, Tim Andeen wrote:
> Hi John, Finished with 6.4.1. Best, Tim
>
> On Thu, Nov 21, 2019 at 3:13 AM John Parsons <parsons AT nevis.columbia.edu
> <mailto:parsons AT nevis.columbia.edu>> wrote:
>
>
>
>
> -------- Forwarded Message --------
> Subject: Re: [Usatlas-hllhc-l2l3ics-l] November Status Sheets
> Date: Thu, 21 Nov 2019 00:17:45 +0000
> From: Freedman, Rhoumela <rfreedman AT bnl.gov
> <mailto:rfreedman AT bnl.gov>>
> To: usatlas-hllhc-l2l3ics-l AT lists.bnl.gov
> <mailto:usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>
> <usatlas-hllhc-l2l3ics-l AT lists.bnl.gov
> <mailto:usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>>
>
>
>
> Good evening!
>
> It has been pointed out to me that there were mistakes on the links
> below. I am resending with the updated links:
>
> ·6.01 Pixels -
> https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_13guiKvwYWRDJoxJtcgua0ZAy5zoMIlreiO7y6qQhNjw_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=ndOZ5l-CBmQuE3LaJeUjNHwK8fAJfMrSCXJLh1i00qA&s=MCv1Jb9Zg-etkqyl3t41UmAq52SjE9Ebkz5f_JsCYGk&e=
>
>
> ·6.02 Strips -
> https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1wYxkGd9UrytehZ-2DB2-2DFj6W64rN3VpxMcokkiakU-2Dp-5Fo_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=ndOZ5l-CBmQuE3LaJeUjNHwK8fAJfMrSCXJLh1i00qA&s=0V-0Y6IFVN4g1UmPzr5WnaUwcm6iydpJ-zQm4qqYsqk&e=
>
>
> ·6.03 Global Mechanics -
> https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_15G0C6i08JeL2VNI3WmUGAJ-2D597MwefKbzf4xc-2DAnrAE_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=ndOZ5l-CBmQuE3LaJeUjNHwK8fAJfMrSCXJLh1i00qA&s=QycTO-QNfpDXDISRfZZGNEn_nrIWwStJA5Su_rqZHKg&e=
>
>
> ·6.04 LAr -
> https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1ROYkQ2iR4xiQ4yur-2DsyDnzbsDueNspQJwhp9tykF7pU_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=ndOZ5l-CBmQuE3LaJeUjNHwK8fAJfMrSCXJLh1i00qA&s=C_fWXiMEAx4Gmcb6XOwKwGES3JJ41PFF6uZw5XkqG-E&e=
>
>
> ·6.05 Tile -
> https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1LOaWOJLnjIDiUsn5P-5Fb-2D-5F1g4-2Du40tHvL-5FWKNmlmzHP8_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=ndOZ5l-CBmQuE3LaJeUjNHwK8fAJfMrSCXJLh1i00qA&s=4GuLQ_cLEYoTh3gdhZFp1bLSdFZevaQqIiFZYD1k1h8&e=
>
>
> ·6.06 Muon -
> https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1GYf3gzXzhlAqIhzKYmlSqfwMqdcmtZnuvNFYKXUzGMY_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=ndOZ5l-CBmQuE3LaJeUjNHwK8fAJfMrSCXJLh1i00qA&s=qQz33Uty0huOBy5dOGKy0Dbbz5uqZ2xYaqO5Xs3EnV0&e=
>
>
> ·6.07 DAQ -
> https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1D0nnHAl4gDtG5tRmJA9OVOtEPi4cmfmTf-5FX4xu-5Fr4Ao_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=ndOZ5l-CBmQuE3LaJeUjNHwK8fAJfMrSCXJLh1i00qA&s=kCpG8ryBjR3A434TQYi4z-K5wxG5CHu4nj_thf3vOLU&e=
>
>
> ·6.08 Trigger -
> https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_10Fr-5Fk-2DgfS0j34sTOe96xMNnOU7CBsyf4E4omotU1QBk_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=ndOZ5l-CBmQuE3LaJeUjNHwK8fAJfMrSCXJLh1i00qA&s=B_cr4ya4XL3BjCg-7jFGW1uUrISV4i0U0UHD6O9BbgM&e=
>
>
> Also, please send me the completed status by Wednesday, November 27.
>
> My apologies for the confusion.
>
> Please let me know if you have any other issues or questions.
>
> Thank you,
>
> Rhoumela
>
> *From:* Usatlas-hllhc-l2l3ics-l
> <usatlas-hllhc-l2l3ics-l-bounces AT lists.bnl.gov
> <mailto:usatlas-hllhc-l2l3ics-l-bounces AT lists.bnl.gov>> *On Behalf
> Of *Freedman,
> Rhoumela
> *Sent:* Wednesday, November 20, 2019 4:26 PM
> *To:* usatlas-hllhc-l2l3ics-l AT lists.bnl.gov
> <mailto:usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>
> *Subject:* [Usatlas-hllhc-l2l3ics-l] November Status Sheets
> *Importance:* High
>
> Dear All,
>
> *If you need help pleaseDO NOT reply to the mailing list*
>
> **** The Pre-Status Reports for November 2019 have been uploaded in
> *DocDB 976*. These are the Gantt Charts for each subsystem. Please
> make
> sure to look over the chart while doing your Status Updates. ****
>
> The status sheets for the month of November are now available in
> google docs
>
> * 6.01 - Pixels -
>
> https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_13guiKvwYWRDJoxJtcgua0ZAy5zoMIlreiO7y6qQhNjw_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=ndOZ5l-CBmQuE3LaJeUjNHwK8fAJfMrSCXJLh1i00qA&s=MCv1Jb9Zg-etkqyl3t41UmAq52SjE9Ebkz5f_JsCYGk&e=
>
>
> * 6.02 - Strips -
>
> https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_15G0C6i08JeL2VNI3WmUGAJ-2D597MwefKbzf4xc-2DAnrAE_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=ndOZ5l-CBmQuE3LaJeUjNHwK8fAJfMrSCXJLh1i00qA&s=QycTO-QNfpDXDISRfZZGNEn_nrIWwStJA5Su_rqZHKg&e=
>
>
> * 6.03 - Global Mechanics -
>
> https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1D0nnHAl4gDtG5tRmJA9OVOtEPi4cmfmTf-5FX4xu-5Fr4Ao_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=ndOZ5l-CBmQuE3LaJeUjNHwK8fAJfMrSCXJLh1i00qA&s=kCpG8ryBjR3A434TQYi4z-K5wxG5CHu4nj_thf3vOLU&e=
>
>
> * 6.04 - LAr -
>
> https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1LOaWOJLnjIDiUsn5P-5Fb-2D-5F1g4-2Du40tHvL-5FWKNmlmzHP8_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=ndOZ5l-CBmQuE3LaJeUjNHwK8fAJfMrSCXJLh1i00qA&s=4GuLQ_cLEYoTh3gdhZFp1bLSdFZevaQqIiFZYD1k1h8&e=
>
>
> * 6.05 - Tile -
>
> https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1GYf3gzXzhlAqIhzKYmlSqfwMqdcmtZnuvNFYKXUzGMY_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=ndOZ5l-CBmQuE3LaJeUjNHwK8fAJfMrSCXJLh1i00qA&s=qQz33Uty0huOBy5dOGKy0Dbbz5uqZ2xYaqO5Xs3EnV0&e=
>
>
> * 6.06 - Muon -
>
> https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1ROYkQ2iR4xiQ4yur-2DsyDnzbsDueNspQJwhp9tykF7pU_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=ndOZ5l-CBmQuE3LaJeUjNHwK8fAJfMrSCXJLh1i00qA&s=C_fWXiMEAx4Gmcb6XOwKwGES3JJ41PFF6uZw5XkqG-E&e=
>
>
> * 6.07 - DAQ -
>
> https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1wYxkGd9UrytehZ-2DB2-2DFj6W64rN3VpxMcokkiakU-2Dp-5Fo_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=ndOZ5l-CBmQuE3LaJeUjNHwK8fAJfMrSCXJLh1i00qA&s=0V-0Y6IFVN4g1UmPzr5WnaUwcm6iydpJ-zQm4qqYsqk&e=
>
>
> * 6.08 - Trigger -
>
> https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_10Fr-5Fk-2DgfS0j34sTOe96xMNnOU7CBsyf4E4omotU1QBk_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=ndOZ5l-CBmQuE3LaJeUjNHwK8fAJfMrSCXJLh1i00qA&s=B_cr4ya4XL3BjCg-7jFGW1uUrISV4i0U0UHD6O9BbgM&e=
>
>
>
> Please remember to update the status online – DO NOT download the files.
>
> The reports are at L2. The reports contain activities for October
> 2019-September 2020 in case some activities have started earlier. You
> can filter for your CAM name in column D.
>
> Please provide status in columns L, M, N, and O. Make sure that you
> enter the actual start date for all started activities and finish date
> for all activities that are 100% completed, this information is crucial
> when we update the schedule in P6. If the activity is completed but you
> do not remember the exact start and finish dates you can enter your
> best
> estimate or copy the dates from the baseline start and finish dates (BL
> Project Start/BL Project Finish). Do NOT enter dates after November 30,
> 2019 in actual start/finish dates (columns M and N) , this creates
> errors in P6. Also do not write any notes in the spreadsheet, we may
> add
> a column for comments in the future.
>
> Please complete the October status update by Tuesday, November 27.
>
> We expect that the L2 managers and deputies will notify us (Penka,
> Carrie, Jenn, Rhoumela) as soon as the status for their system is
> complete.
>
> Let us know if you have any questions or comments/suggestions to make
> the process smoother and more user-friendly.
>
> Thank you!
>
> Rhoumela Freedman, Administrator
>
> U.S. ATLAS HL-LHC Upgrade Project
>
> Brookhaven National Laboratory, Physics Dept.
>
> Tel: (631) 344-3460
>
> Fax: (631) 344-6179
>
> rfreedman AT bnl.gov <mailto:rfreedman AT bnl.gov>
> <mailto:rfreedman AT bnl.gov <mailto:rfreedman AT bnl.gov>>
>
> _______________________________________________
> Usatlas-hllhc-lartl2l3-l mailing list
> Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
> <mailto:Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
> https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-lartl2l3-l
>
>
>
> --
> ---------------
> Tim Andeen
> Assistant Professor, Department of Physics
> College of Natural Sciences
> The University of Texas at Austin
> Austin, TX 78712-1192
> web: tandeen.web.cern.ch <http://tandeen.web.cern.ch>
> office (TX): PMA 10.208
> office (CERN): 304/1-024
> ph (TX): +1 512 475-9575
> ph (CERN): +41 (0)22 76 758 14
> email: tandeen AT utexas.edu <mailto:tandeen AT utexas.edu>
> ---------------
--
______________________________________________________________________
John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW: http://www.nevis.columbia.edu/~parsons/
______________________________________________________________________
---------------
Tim Andeen
Assistant Professor, Department of Physics
College of Natural Sciences
The University of Texas at Austin
Austin, TX 78712-1192
web: tandeen.web.cern.ch
office (TX): PMA 10.208
office (CERN): 304/1-024
ph (TX): +1 512 475-9575
ph (CERN): +41 (0)22 76 758 14
email: tandeen AT utexas.edu
---------------
Tim Andeen
Assistant Professor, Department of Physics
College of Natural Sciences
The University of Texas at Austin
Austin, TX 78712-1192
web: tandeen.web.cern.ch
office (TX): PMA 10.208
office (CERN): 304/1-024
ph (TX): +1 512 475-9575
ph (CERN): +41 (0)22 76 758 14
email: tandeen AT utexas.edu
---------------
-
[Usatlas-hllhc-lartl2l3-l] Fwd: Re: [Usatlas-hllhc-l2l3ics-l] November Status Sheets,
John Parsons, 11/20/2019
-
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: Re: [Usatlas-hllhc-l2l3ics-l] November Status Sheets,
Tim Andeen, 11/22/2019
-
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: Re: [Usatlas-hllhc-l2l3ics-l] November Status Sheets,
John Parsons, 11/23/2019
- Re: [Usatlas-hllhc-lartl2l3-l] Fwd: Re: [Usatlas-hllhc-l2l3ics-l] November Status Sheets, Tim Andeen, 11/24/2019
-
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: Re: [Usatlas-hllhc-l2l3ics-l] November Status Sheets,
John Parsons, 11/23/2019
-
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: Re: [Usatlas-hllhc-l2l3ics-l] November Status Sheets,
Tim Andeen, 11/22/2019
Archive powered by MHonArc 2.6.24.