Hi all,
The PO is getting more stringent about the monthly variance reports. In particular, they are insisting I comment on our CPI (in addition to delays). For December (see attached), our CPI is 1.12 at L2, meaning the actual work done has been 12% cheaper than planned, and we need to explain why. More significantly, the +12% at L2 masks some much larger variations at L3/L4. Here is the breakdown:
6.4.1 Columbia = 1.00, UTA = 1.33, SMU = 1.36
ie. both of UTA and SMU are >30 underspent for the work done. Tim, you need to explain why that is.
6.4.2 Columbia = 0.96 (no report needed)
6.4.3 SBU = -11%, U Az = +3%
ie. Andy, SBU is 11% OVERspent, despite us claiming they used extra uncosted labor due to the new hire
6.4.4 BNL = +160% (!!) underspent
Hao, we need an explanation why
6.4.5 BNL = -12%
Hong, we need an explanation why it is overspent
This is urgent, so please get back to me right away with input for your L3 that I can include in the December VR (just in time to start working on the VR for January!).
Thanks,
John
--
______________________________________________________________________
John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW:
https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!RfFzv38ZI5cNq0oBUyMU4QE1V2qUU6yJe-l-vkWdwwdjOqHK3eMWXi4BV73XhR6KEaBj1C1Q-a5g6c8AdSvY$
______________________________________________________________________
Attachment:
201912 CPR ALL.xlsx
Description: application/vnd.openxmlformats-officedocument.spreadsheetml.sheet
- [Usatlas-hllhc-lartl2l3-l] input needed urgently for VR for December, John Parsons, 02/04/2020
Archive powered by MHonArc 2.6.24.