Skip to Content.
Sympa Menu

usatlas-hllhc-lartl2l3-l - [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] April 2020 Status Validation Reports

usatlas-hllhc-lartl2l3-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List

List archive

Chronological Thread  
  • From: John Parsons <parsons AT nevis.columbia.edu>
  • To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
  • Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] April 2020 Status Validation Reports
  • Date: Fri, 8 May 2020 13:04:20 -0400


Take a look at let me know of any problems.



-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2l3ics-l] April 2020 Status Validation Reports
Date: Fri, 8 May 2020 16:27:44 +0000
From: Novakova, Penka N <penka AT bnl.gov>
To: usatlas-hllhc-l2l3ics-l AT lists.bnl.gov <usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>



Dear All,

The  April 2020 Status Validation Reports are uploaded in IPD (https://ipdv2.bnl.gov/overview/reports.aspx).

They are also available in DocDB 1017 (https://atlas-hllhc.docdb.bnl.gov/cgi-bin/private/ShowDocument?docid=1017 ).  (Please use your L2 or team username and password to access the reports)

The PDF for each system show only activities **in progress** or activities with an actual finish date in April.

Please review the reports, the goal is to make sure that the status you have provided was implemented in P6 correctly. If there are issues please let us know no later than 12 PM (EST) Monday*, May 11*.

Thank you,

Penka

_______________________________________________
Usatlas-hllhc-l2l3ics-l mailing list
Usatlas-hllhc-l2l3ics-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2l3ics-l


  • [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] April 2020 Status Validation Reports, John Parsons, 05/08/2020

Archive powered by MHonArc 2.6.24.

Top of Page