Skip to Content.
Sympa Menu

usatlas-hllhc-lartl2l3-l - Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] June 2020 Status Sheets

usatlas-hllhc-lartl2l3-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List

List archive

Chronological Thread  
  • From: John Parsons <parsons AT nevis.columbia.edu>
  • To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
  • Subject: Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] June 2020 Status Sheets
  • Date: Mon, 22 Jun 2020 21:35:19 -0400


A reminder to take care of these items by COB tomorrow.

Thanks,
John

On 6/19/20 10:32 AM, John Parsons wrote:

Hi all,

    It is monthly status report and technical bullets time again. Please take care of both of these things by COB next Tuesday.
    Thanks,
        John

-------- Forwarded Message --------
Subject:     [Usatlas-hllhc-l2l3ics-l] June 2020 Status Sheets
Date:     Fri, 19 Jun 2020 13:31:52 +0000
From:     Freedman, Rhoumela <rfreedman AT bnl.gov>
To:     usatlas-hllhc-l2l3ics-l AT lists.bnl.gov <usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>



Dear All,

*If you need help pleaseDO NOT reply to the mailing list*

**** The */Pre-Status Reports/*/*for June 2020*/ have been uploaded in *DocDB 976*. These are the Gantt Charts for each subsystem.  Please make sure to look over the chart while doing your Status Updates. ****

The status sheets for the month of May are now available in google docs:

·6.01 - Pixels - https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1hEVP-uvuGwKJ2xyBC9y7NddVpM1FcWrHVkxazjwcZj0/edit?usp=sharing,*20__;JQ!!P4SdNyxKAPE!VYTqcjQHaWs5E_CNUL7sjPere2NDo5YyfQCZ2n55Fx5qB9vcJeYtwr6irJHCWyaxXLVYKmE2uK3Qkcp5_amN$

·6.02 - Strips - https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1UpZaE6PDRvTec3VLjAWProYam0JekF679YmNFHpXJEY/edit?usp=sharing,*20__;JQ!!P4SdNyxKAPE!VYTqcjQHaWs5E_CNUL7sjPere2NDo5YyfQCZ2n55Fx5qB9vcJeYtwr6irJHCWyaxXLVYKmE2uK3QkVWY9ZXP$

·6.03 - GM -https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1LWJFB2MDoHF44IHMQ4dUig7WgV78a8u_SgjLb2Yothk/edit?usp=sharing,*20__;JQ!!P4SdNyxKAPE!VYTqcjQHaWs5E_CNUL7sjPere2NDo5YyfQCZ2n55Fx5qB9vcJeYtwr6irJHCWyaxXLVYKmE2uK3QkQQhOed1$

·6.04 - LAr - https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/16IHtkCRb3qnsTgJFMJUAw1__5um83S2yH6DGX21Bnh0/edit?usp=sharing,*20__;JQ!!P4SdNyxKAPE!VYTqcjQHaWs5E_CNUL7sjPere2NDo5YyfQCZ2n55Fx5qB9vcJeYtwr6irJHCWyaxXLVYKmE2uK3QkXZ2iZT7$

·6.05 - Tiles - https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/17I3CjfiFmmDYKUFs7JJC4AOcXL-Gsp9lotMmtldO_rU/edit?usp=sharing,*20__;JQ!!P4SdNyxKAPE!VYTqcjQHaWs5E_CNUL7sjPere2NDo5YyfQCZ2n55Fx5qB9vcJeYtwr6irJHCWyaxXLVYKmE2uK3QkSp2i9hf$

·6.06 - Muons - https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1O217nJcsRGo3E_kOoSF1o2RMFsjDv-YKB7t43vakyAM/edit?usp=sharing,*20__;JQ!!P4SdNyxKAPE!VYTqcjQHaWs5E_CNUL7sjPere2NDo5YyfQCZ2n55Fx5qB9vcJeYtwr6irJHCWyaxXLVYKmE2uK3QkX0-XWce$

·6.07 - DAQ - https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1o9kkkCNOwqUYw9fFnEtyg2s9FCiaDrNNYv22r8dBcTY/edit?usp=sharing__;!!P4SdNyxKAPE!VYTqcjQHaWs5E_CNUL7sjPere2NDo5YyfQCZ2n55Fx5qB9vcJeYtwr6irJHCWyaxXLVYKmE2uK3QkavcHpJp$

·6.08 - Trigger - https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1KZjhfq5tBTV1w5R_ePkamm4tORMMFk9xUucvyxY6vGo/edit?usp=sharing,*20__;JQ!!P4SdNyxKAPE!VYTqcjQHaWs5E_CNUL7sjPere2NDo5YyfQCZ2n55Fx5qB9vcJeYtwr6irJHCWyaxXLVYKmE2uK3QkU1XKSmw$

Please remember to update the status online – DO NOT download the files.

The reports are at L2. The reports contain activities for October 2019-September 2020. You can filter for your CAM name in column D.

**** PLEASE NOTE THE FOLLOWING INSTRUCTIONS IN FILLING OUT YOUR STATUS SHEETS: ****

 1. In this months’ status sheets we have added new column for resources
    (column O) and Planned/Remaining Units (hours for labor and direct
    cost for material/travel) in columns P and Q. The remaining units
    are calculated based on the original duration of the activity and
    percent complete. We have added *column R* in which we are asking
    you to update the **Units to Complete** based on your experience and
    expectations. This is only in case you expect to spend more or less
    labor for the specific activity or the cost for material/travel is
    different than originally estimated. Column S show Total Cost per
    resource  from P6. Columns T (Remaining Cost based on the remaining
    units from P6), U (Updated Remaining Cost, also called ETC or
    Estimate-to-Complete), V (EAC or Estimate at Complete, calculated
    based on updated units) and W (Delta EAC minus baseline cost) are
    formula fields that provide calculations on how the cost changes
    when the Remaining Units are adjusted.
 2. Please provide status in columns K, L, M, N, and R. Make sure that
    for all activities in progress you provide **Expected Finish**
    (column N). This is important for us to re-calculate the float and
    the critical path.
 3. Make sure that you enter the actual start date for all started
    activities and finish date for all activities that are 100%
    completed. All *_NEW_* actual start and finish dates *MUST BE*
    within current reporting period.
 4. Do *NOT *change the actual start/finish dates if they are already in
    the spreadsheet – EVMS does not allow changing the past. If the
    actual start date was entered incorrectly in the previous month just
    leave it as it is.
 5. Do *NOT* enter dates after June 30, 2020  in actual start/finish
    dates (columns L and M) , this creates errors in P6.
 6. Do *NOT* decrease percent complete in column K.
 7. Do *NOT* write any notes in the spreadsheet, if you want to add a
    comment use column X.

*_Additional Note: _*

If progress was made on future activities that are not in the status sheet you can contact your project controls specialist and ask for her help with statussing the activities directly in P6. This should be done the week of June 29^th after the status is provided to us.

Please complete the May status update by Friday, June 26.

We expect that the L2 managers and deputies will notify us (Penka,  Carrie, Jenn, Rhoumela) as soon as the status for their system is complete.

Let us know if you have any questions or comments/suggestions to make the process smoother and more user-friendly.

Thank you!

Rhoumela Freedman, Administrator

U.S. ATLAS HL-LHC Upgrade Project

Brookhaven National Laboratory, Physics Dept.

Tel: (631) 344-3460

Fax: (631) 344-6179

rfreedman AT bnl.gov <mailto:rfreedman AT bnl.gov>


--
______________________________________________________________________

John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW:
https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!VYTqcjQHaWs5E_CNUL7sjPere2NDo5YyfQCZ2n55Fx5qB9vcJeYtwr6irJHCWyaxXLVYKmE2uK3QkckA4CLu$


______________________________________________________________________




Archive powered by MHonArc 2.6.24.

Top of Page