  • From: John Parsons <parsons AT nevis.columbia.edu>
  • To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
  • Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] July 2020 Status Sheets
  • Date: Mon, 20 Jul 2020 16:22:05 -0400


It is monthly status report and technical bullets time again. Please take care of both by COB this Thursday.

John

-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2l3ics-l] July 2020 Status Sheets
Date: Mon, 20 Jul 2020 20:15:35 +0000
From: Freedman, Rhoumela <rfreedman AT bnl.gov>
To: usatlas-hllhc-l2l3ics-l AT lists.bnl.gov <usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>



Dear All,

*If you need help pleaseDO NOT reply to the mailing list*

**** The */Pre-Status Reports/*/*for July 2020*/ have been uploaded in *DocDB 976*. These are the Gantt Charts for each subsystem.  Please make sure to look over the chart while doing your Status Updates. ****

The status sheets for the month of July are now available in google docs:

·6.01 - Pixels - https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1J6o8Ie9-usHNKrKmqiTrZARlE_zInPuSixEwS2UEF_w/edit?usp=sharing__;!!P4SdNyxKAPE!RAI0GP1yxjMBzIHswpv5g5TjOaDsnhs_ZBsKNdzkdjvgbu__gua2Xt6-nwxPbCBwyNEA7QYTsevieiPDwUsx$
·6.02 - Strips - https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1sRsiuOaafKXkPowXeRqTwWhHnyZ1OMZp3SrxmEhyRTM/edit?usp=sharing__;!!P4SdNyxKAPE!RAI0GP1yxjMBzIHswpv5g5TjOaDsnhs_ZBsKNdzkdjvgbu__gua2Xt6-nwxPbCBwyNEA7QYTsevieqOe_xoB$
·6.03 - Global Mechanics - https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1CKfl56x4jqQakgBQ9tNCxWkXHtWEmBmwbjA58s0WOPI/edit?usp=sharing__;!!P4SdNyxKAPE!RAI0GP1yxjMBzIHswpv5g5TjOaDsnhs_ZBsKNdzkdjvgbu__gua2Xt6-nwxPbCBwyNEA7QYTsevieiFjxxXB$
·6.04 - LAr - https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/158h6DdOA0Qq4ahvoCCB-ae4bUlYm-u1RhOUeOPAc-Qw/edit?usp=sharing__;!!P4SdNyxKAPE!RAI0GP1yxjMBzIHswpv5g5TjOaDsnhs_ZBsKNdzkdjvgbu__gua2Xt6-nwxPbCBwyNEA7QYTsevieptxGwP4$
·6.05 - Tiles - https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1_RKPM5Mm2uVQi1nveEHgFsyD3NZwrn2HiOkAwLqyyqY/edit?usp=sharing__;!!P4SdNyxKAPE!RAI0GP1yxjMBzIHswpv5g5TjOaDsnhs_ZBsKNdzkdjvgbu__gua2Xt6-nwxPbCBwyNEA7QYTseviegTX0jwA$
·6.06 - Muons - https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1UD0N7mCe6HzXzo225FDBxmPPuJSbPq6659E7WlyZc14/edit?usp=sharing__;!!P4SdNyxKAPE!RAI0GP1yxjMBzIHswpv5g5TjOaDsnhs_ZBsKNdzkdjvgbu__gua2Xt6-nwxPbCBwyNEA7QYTsevieh77i5zV$
·6.07 - DAQ - https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1g4VvYauVGcec6fDvEIWwjwKJK8tv8tFjEjuJV4LdOyk/edit?usp=sharing__;!!P4SdNyxKAPE!RAI0GP1yxjMBzIHswpv5g5TjOaDsnhs_ZBsKNdzkdjvgbu__gua2Xt6-nwxPbCBwyNEA7QYTseviepNzVFVU$
·6.08 - Trigger - https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1DPTEbMim0yvJ6eu5XEsspJSMEUvMI1-TMmtlc83C8U8/edit?usp=sharing__;!!P4SdNyxKAPE!RAI0GP1yxjMBzIHswpv5g5TjOaDsnhs_ZBsKNdzkdjvgbu__gua2Xt6-nwxPbCBwyNEA7QYTseviek6vgNk5$
Please remember to update the status online – DO NOT download the files.

The reports are at L2. The reports contain activities for July 2020-January 2021. You can filter for your CAM name in column D.

**** PLEASE NOTE THE FOLLOWING INSTRUCTIONS IN FILLING OUT YOUR STATUS SHEETS: *** *

1. In this months’ status sheets we have added new column for resources
(column O) and Planned/Remaining Units (hours for labor and direct
cost for material/travel) in columns P and Q. The remaining units
are calculated based on the original duration of the activity and
percent complete. We have added *column R* in which we are asking
you to update the **Units to Complete** based on your experience and
expectations. This is only in case you expect to spend more or less
labor for the specific activity or the cost for material/travel is
different than originally estimated. Column S show Total Cost per
resource  from P6. Columns T (Remaining Cost based on the remaining
units from P6), U (Updated Remaining Cost, also called ETC or
Estimate-to-Complete), V (EAC or Estimate at Complete, calculated
based on updated units) and W (Delta EAC minus baseline cost) are
formula fields that provide calculations on how the cost changes
when the Remaining Units are adjusted.
2. Please provide status in columns K, L, M, N, and R. Make sure that
for all activities in progress you provide **Expected Finish**
(column N). This is important for us to re-calculate the float and
the critical path.
3. Make sure that you enter the actual start date for all started
activities and finish date for all activities that are 100%
completed. All *_NEW_* actual start and finish dates *MUST BE*
within current reporting period.
4. Do *NOT *change the actual start/finish dates if they are already in
the spreadsheet – EVMS does not allow changing the past. If the
actual start date was entered incorrectly in the previous month just
leave it as it is.
5. Do *NOT* enter dates after July 31, 2020  in actual start/finish
dates (columns L and M) , this creates errors in P6.
6. Do *NOT* decrease percent complete in column K.
7. Do *NOT* write any notes in the spreadsheet, if you want to add a
comment use column X.
8. Do *NOT* change the formatting of the cell once you edit it.  The
spreadsheet will automatically highlight the change in yellow.
*_Additional Note: _*

If progress was made on future activities that are not in the status sheet you can contact your project controls specialist and ask for her help with statussing the activities directly in P6. This should be done the week of August 3rd after the status is provided to us.

Please complete the July status update by Monday, July 27.

We expect that the L2 managers and deputies will notify us (Penka,  Carrie, Jenn, Rhoumela) as soon as the status for their system is complete.

Let us know if you have any questions or comments/suggestions to make the process smoother and more user-friendly.

Thank you!

Rhoumela Freedman, Administrator

U.S. ATLAS HL-LHC Upgrade Project

Brookhaven National Laboratory, Physics Dept.

Tel: (631) 344-3460

Fax: (631) 344-6179

rfreedman AT bnl.gov <mailto:rfreedman AT bnl.gov>

_______________________________________________
Usatlas-hllhc-l2l3ics-l mailing list
Usatlas-hllhc-l2l3ics-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2l3ics-l


  • [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] July 2020 Status Sheets, John Parsons, 07/20/2020