Here is the clarification from Gustaaf.
Hong.
From:
Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
Hi,
I think we all agree that we don't want to have, one year from now, old tasks at 0% that we will never complete. So we can either mark them complete or delete them.
I think if the travel doesn't happen because of COVID, and we are in the middle of doing a COVID BCP, the preference is obviously to delete the tasks in question.
For NSF, it's not at all clear that they'll let us do the COVID BCP, so there the situation is a bit different. Given that travel is such a small fraction of the project, it may then be easier to just mark those tasks complete. I don't think that's inherently cheating, it's equivalent to a task that was easier than foreseen and required fewer resources.
That said, I think sometime next year we're going to have to revisit all the travel in the project, as travel specifically for eg FDRs or PRRs will certainly come to an end. Such meetings will become online-only fr the long term.
Best,
Gustaaf
From: Ma, Hong <hma AT bnl.gov>
The DOE part of the COVID impact is being evaluated. During the preparation, Jenn pointed out that a couple of travel tasks were not completed, while the associated design work was completed. Therefore, the task will be removed, along with the funding associated with the task. At today L2 meeting, it was pointed out that if a travel could not happen because of COVID, but the relevant work was carried out via teleconference, then the task can be marked as complete, and you get to keep the funding. If you have similar cases, please consider the option.
Hong. |
-
[Usatlas-hllhc-lartl2l3-l] FW: COVID impact,
Freedman, Rhoumela, 09/18/2020
- <Possible follow-up(s)>
- Re: [Usatlas-hllhc-lartl2l3-l] FW: COVID impact, Ma, Hong, 09/19/2020
Archive powered by MHonArc 2.6.24.