Skip to Content.
Sympa Menu

usatlas-hllhc-lartl2l3-l - [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: Scheduling the NSF review of the HL upgrade to ATLAS

usatlas-hllhc-lartl2l3-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List

List archive

Chronological Thread  
  • From: John Parsons <parsons AT nevis.columbia.edu>
  • To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
  • Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: Scheduling the NSF review of the HL upgrade to ATLAS
  • Date: Mon, 5 Apr 2021 12:05:49 -0400


FYI. Let me know of any problems with those dates.

-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: Scheduling the NSF review of the HL upgrade to ATLAS
Date: Mon, 5 Apr 2021 13:57:53 +0000
From: Michael Tuts <tuts AT pmtuts.net>
To: Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov <Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>, us-atlas-hllhc-pmgmt-l AT lists.bnl.gov <us-atlas-hllhc-pmgmt-l AT lists.bnl.gov>



Dear NSF L2 and Dep,

This is the latest communication we have had regarding the upcoming NSF review. August was one of the periods available to all (at the time). Can you indicte if any of these dates are a problem for a 1 day Zoom review.

Thanks, Mike

*From:* Coles, Mark W. <mcoles AT nsf.gov>
*Sent:* Monday, April 5, 2021 9:08 AM
*To:* Michael Tuts <tuts AT pmtuts.net>
*Cc:* Stein, Erica M. <estein AT nsf.gov>; Yasky, Rebecca Kay <ryasky AT nsf.gov>
*Subject:* Scheduling the NSF review of the HL upgrade to ATLAS

Hi Mike

I would like to fix the date for NSF’s review of ATLAS construction progress. Could you please check with your colleagues to see if we can have a one-day review on one of these days: August 17, 18, or 19 (T, W, Th)? This will be a Zoom meeting.

Thanks

Mark



_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l


  • [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: Scheduling the NSF review of the HL upgrade to ATLAS, John Parsons, 04/05/2021

Archive powered by MHonArc 2.6.24.

Top of Page