usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List
List archive
[Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Second NSF COVID-19 change
- From: John Parsons <parsons AT nevis.columbia.edu>
- To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
- Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Second NSF COVID-19 change
- Date: Thu, 22 Apr 2021 20:10:34 -0400
FYI for Tim and Andy; you should have received this directly. We will discuss it tomorrow, but this is urgent.
-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2l3ics-l] Second NSF COVID-19 change
Date: Tue, 20 Apr 2021 20:18:01 +0000
From: Novakova, Penka N <penka AT bnl.gov>
To: usatlas-hllhc-l2l3ics-l AT lists.bnl.gov <usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>
This message is for NSF CAMs only
As discussed we will start working on the SECOND NSF COVID-19 change request. For this purpose Carrie has generated excel spreadsheets and Rhoumela has posted them in google docs
* 6.04 – LAr -
https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1QWSG-a7n2oD9X0KVtFDRCFEUkqofRvtuPAcdCDcz90o/edit?usp=sharing__;!!P4SdNyxKAPE!Vp_SMAuY1suKa-jqrL5D1Q8v8oRwctZhCsgRN9C4DYaa0xskfBqI384ri5JSN3FXn87GfjODdBTETmWJC9sm$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1QWSG-a7n2oD9X0KVtFDRCFEUkqofRvtuPAcdCDcz90o/edit?usp=sharing__;!!P4SdNyxKAPE!Vp_SMAuY1suKa-jqrL5D1Q8v8oRwctZhCsgRN9C4DYaa0xskfBqI384ri5JSN3FXn87GfjODdBTETmWJC9sm$
>
* 6.05 - Tile -
https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1i7Le2ipE_gn6Gd4Hyi9iL-IvEazdH5N7cOtOflbXU3E/edit?usp=sharing__;!!P4SdNyxKAPE!Vp_SMAuY1suKa-jqrL5D1Q8v8oRwctZhCsgRN9C4DYaa0xskfBqI384ri5JSN3FXn87GfjODdBTETnyz0q0g$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1i7Le2ipE_gn6Gd4Hyi9iL-IvEazdH5N7cOtOflbXU3E/edit?usp=sharing__;!!P4SdNyxKAPE!Vp_SMAuY1suKa-jqrL5D1Q8v8oRwctZhCsgRN9C4DYaa0xskfBqI384ri5JSN3FXn87GfjODdBTETnyz0q0g$
>
* 6.06 – Muon -
https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1xuIItCCx-VBOUASbdIcNSfQM-MK_AYStmTLzzqoPIaU/edit?usp=sharing__;!!P4SdNyxKAPE!Vp_SMAuY1suKa-jqrL5D1Q8v8oRwctZhCsgRN9C4DYaa0xskfBqI384ri5JSN3FXn87GfjODdBTETruL4ESA$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1xuIItCCx-VBOUASbdIcNSfQM-MK_AYStmTLzzqoPIaU/edit?usp=sharing__;!!P4SdNyxKAPE!Vp_SMAuY1suKa-jqrL5D1Q8v8oRwctZhCsgRN9C4DYaa0xskfBqI384ri5JSN3FXn87GfjODdBTETruL4ESA$
>
* 6.08 – Trigger -
https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/10lKFeaORd0XDYIox2u_FhHLRIgwRmucCidSvCoAOwiA/edit?usp=sharing__;!!P4SdNyxKAPE!Vp_SMAuY1suKa-jqrL5D1Q8v8oRwctZhCsgRN9C4DYaa0xskfBqI384ri5JSN3FXn87GfjODdBTETniF0cjt$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/10lKFeaORd0XDYIox2u_FhHLRIgwRmucCidSvCoAOwiA/edit?usp=sharing__;!!P4SdNyxKAPE!Vp_SMAuY1suKa-jqrL5D1Q8v8oRwctZhCsgRN9C4DYaa0xskfBqI384ri5JSN3FXn87GfjODdBTETniF0cjt$
>
Do not use the **minus** (collapse) sign when editing the sheets – this may corrupt the updates made by other CAMs.
We will be using the same method as in the previous COVID-19 change (see attached Gustaaf’s presentation).
Detailed instructions are provided below.
The sheets are based on the March status working schedule. They are similar to the status sheets but have some differences.
In the sheets there are 2 tabs
1. In-progress activities
2. Not started activities that have baseline dates between November 1,
2020 and September 30, 2021
For **in-progress** activities
Activities will be split – the first activity will have baseline start as in the current schedule and completion date of May 1, 2021 and will be set up to **completed** in the May status. The second activity will have the same description with **(2)** at the end. Therefore we are *not* asking you to add new activity but rather provide information for this second activity in columns W (duration), X(start date), Y(finish date), Z(updated effort).
Planned units of the first activity will be calculated based on **Planned Units**(column N) minus **Remaining Units**(column O).
For **Not started** activities.
If you know how their durations/start/finish dates have changed please provide this is columns V, W, X, Y. If you don’t have information leave them as they are. Only change effort and/or duration if task will be done in near future (< 6 months).
Keep in mind that activities with baseline start date before May 1, 2021 should be moved after May 1 otherwise we will get schedule variance once we start statussing the updated schedules.
If you know that travel will not happen add comment in column Z so we know that the activity should be deleted.
We would like to get feedback as soon as possible but not later than *Wednesday, April 28*.
If you have any questions please let us know.
Best,
Penka, Carrie, Jenn, Rhoumela
Penka Novakova
U.S. ATLAS HL-LHC Project Office
Bldg. 510
Brookhaven National Lab
Upton, NY 11973
Tel. 631-344-2502
Attachment:
2020-10-16-COVID-BCP-NSF.pdf
Description: Adobe PDF document
Usatlas-hllhc-l2l3ics-l mailing list
Usatlas-hllhc-l2l3ics-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2l3ics-l_______________________________________________
Usatlas-hllhc-l2l3ics-l mailing list
Usatlas-hllhc-l2l3ics-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2l3ics-l
-
[Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Second NSF COVID-19 change,
John Parsons, 04/22/2021
- Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Second NSF COVID-19 change, Tim Andeen, 04/22/2021
Archive powered by MHonArc 2.6.24.