Skip to Content.
Sympa Menu

usatlas-hllhc-lartl2l3-l - [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] External dependencies and VR tracking

usatlas-hllhc-lartl2l3-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List

List archive

Chronological Thread  
  • From: John Parsons <parsons AT nevis.columbia.edu>
  • To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
  • Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] External dependencies and VR tracking
  • Date: Thu, 8 Jul 2021 14:56:18 -0400


Hi Tim/Andy,

Here is another task for the NSF L3s, needed asap in preparation for the upcoming NSF review. Don't worry about the mention below of external dependencies; I have already completed that task for the entire NSF scope. However, I need you to fill out the VR tracking spreadsheet that is attached. Please do right away and try your best to get it to me tomorrow (sorry!). It should not take too long.
Thanks,
John

-------- Forwarded Message --------
Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] External dependencies and VR tracking
Date: Wed, 23 Jun 2021 16:57:00 +0200
From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
To: usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov


Hi,

Since some were wondering: for the VR tracking sheet, each column is a month. I only filled May 2020, so you have to fill all the other months, just cut-and-paste from ipd for the first 5 rows from each deliverable. (We are trying to get somebody to script that, but it will take a little while.)

For the 6th and 7th rows you then need to add relevant info, see eg the guidance I added for 6.4.3 in the attached example.

Distribute the work to your L3s!

Best,

Gustaaf

On 6/23/21 11:13 AM, Gustaaf Brooijmans wrote:

Hello all,

A couple of requests:

-please send the VR tracking sheets you prepared for the director's review; we'll want to go over them together but it may be useful for us to start with email feedback.

-please start making a list of all the tasks with external dependencies in your schedule.  This includes tasks where you depend on international collaborators as well as tasks where you depend on vendors.  It is likely these will be the major source of covid-induced delays going forward.  Please have this ready by July 1st.

Thanks,

Gustaaf
_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l


Attachment: VR-tracking-v1.xlsx
Description: application/vnd.openxmlformats-officedocument.spreadsheetml.sheet

_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l


  • [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] External dependencies and VR tracking, John Parsons, 07/08/2021

Archive powered by MHonArc 2.6.24.

Top of Page