[Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-doe-l] Scrubbing meetings for DOE review
- From: John Parsons <parsons AT nevis.columbia.edu>
- To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
- Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-doe-l] Scrubbing meetings for DOE review
- Date: Tue, 21 Sep 2021 18:43:46 -0400
FYI
-------- Forwarded Message --------
Subject: Re: [Usatlas-hllhc-l2deputymgmt-doe-l] Scrubbing meetings for DOE review
Date: Tue, 21 Sep 2021 18:21:30 +0000
From: Meyer, Christopher John <cjmey AT iu.edu>
To: usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov <usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov>
CC: George Redlinger (george.redlinger AT cern.ch) <george.redlinger AT cern.ch>, usatlas-hllhc-management-l AT lists.bnl.gov <usatlas-hllhc-management-l AT lists.bnl.gov>
Dear DOE L2s/DL2s,
Thanks a lot for your help scheduling the scrubbing meetings for our upcoming DOE reviews. The final schedule is:
- Pixel: Tues, Sep 28 from 2–4 PM EDT
- Strips: Thurs, Sep 30 from 3–5 PM EDT
- DAQ: Fri, Oct 1 from 4–6 PM EDT
- GM: Mon, Oct 4 from 3–5 PM EDT
- LAr: Friday, Oct 8 from 12:30–2:30 PM EDT
We would propose following the same approach as in the past, namely that we have a presentation by each L3, with one slide per risk (using the template in the “detailed view” tab in the risk register xlsx file). There could be a short overview by the L2, if this would be helpful to understand the overall context. The main things we want to cover are:
- Is everything up to date? (Expiration, cost/schedule impacts, comments, task affected)
- Are there new risks?
- Any questions from the PMO on the existing risk documentation (consistency across risks, comments are sufficiently explanatory)
- COVID vendor risks: expect a more detailed email on this topic soon
* Special to Strips: is the Standing Army analysis up to date? (Maybe this has to be covered by the L2)
The most up-to-date risk register can be found here:
https://atlas-hllhc.docdb.bnl.gov/0001/000196/063/Risk-Register_v61.xlsx <https://atlas-hllhc.docdb.bnl.gov/0001/000196/063/Risk-Register_v61.xlsx>
We are arranging for the usual agendas with connection details and will follow-up when they’re available. In the meantime, please reach out with any questions you may have.
Cheers,
Chris, Chris & George
*From: *Meyer, Christopher John <cjmey AT iu.edu>
*Date: *Tuesday, September 7, 2021 at 3:30 PM
*To: *usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov <usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov>, usatlas-hllhc-management-l AT lists.bnl.gov <usatlas-hllhc-management-l AT lists.bnl.gov>
*Cc: *George Redlinger (george.redlinger AT cern.ch) <george.redlinger AT cern.ch>, Bee, Christopher (Contact) <christopher.bee AT stonybrook.edu>
*Subject: *Scrubbing meetings for DOE review
Dear DOE L2s/DL2s,
In preparation for the upcoming DOE reviews, we'd like to start scheduling scrubbing meetings to update the risk simulation. As a first attempt, would you please respond to Chris, George and myself on your general availability the weeks of Sep 27 and Oct 4? This avoids the upcoming TDAQ week (Sep 20) and ATLAS week (Oct 11).
Thanks,
Chris M, Chris B & George
_______________________________________________
Usatlas-hllhc-l2deputymgmt-doe-l mailing list
Usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-doe-l
-
[Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-doe-l] Scrubbing meetings for DOE review,
John Parsons, 09/07/2021
- Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-doe-l] Scrubbing meetings for DOE review, Ma, Hong, 09/07/2021
- <Possible follow-up(s)>
- [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-doe-l] Scrubbing meetings for DOE review, John Parsons, 09/21/2021
Archive powered by MHonArc 2.6.24.