  • From: John Parsons <parsons AT nevis.columbia.edu>
  • To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
  • Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: ATLAS EVMS Surveillance Review Report
  • Date: Mon, 4 Oct 2021 15:00:12 -0400


FYI


-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: ATLAS EVMS Surveillance Review Report
Date: Fri, 1 Oct 2021 20:25:31 +0000
From: Michael Tuts <tuts AT pmtuts.net>
To: usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>



Dear NSF L2 managers,

Attached is the report from the EVMS surveillance review (Aug17-20). Please distribute to your CAMs.

Thanks, PO

*From:* Coles, Mark W. <mcoles AT nsf.gov>
*Sent:* Friday, October 1, 2021 10:51 AM
*To:* tuts AT nevis.columbia.edu
*Cc:* Yasky, Rebecca Kay <ryasky AT nsf.gov>; Stein, Erica M. <estein AT nsf.gov>; Shank, James T. <jshank AT nsf.gov>
*Subject:* FW: ATLAS EVMS Surveillance Review Report

Hi Mike

The final EVMS surveillance report on the NSF-funded component of the ATLAS HL upgrade is attached. Please contact Rebecca directly, and copy Erica and me, if you or your team have any questions. We appreciate the efforts of your team to provide the information that was used to create this report.

Mark

*From:* Yasky, Rebecca Kay <ryasky AT nsf.gov <mailto:ryasky AT nsf.gov>>
*Sent:* Thursday, September 30, 2021 6:22 PM
*To:* Coles, Mark W. <mcoles AT nsf.gov <mailto:mcoles AT nsf.gov>>
*Cc:* Stein, Erica M. <estein AT nsf.gov <mailto:estein AT nsf.gov>>; Farnsworth, Richard <rfarnswo AT nsf.gov <mailto:rfarnswo AT nsf.gov>>; Hawkins, Matthew J. <mjhawkin AT nsf.gov <mailto:mjhawkin AT nsf.gov>>
*Subject:* ATLAS EVMS Surveillance Review Report

Mark – Attached is the final report for the ATLAS EVMS surveillance review conducted virtually in August 2021.  The review team determined that the ATLAS EVMS continues to meet the intent of EIA-748 guidelines and NSF requirements and that the ATLAS Project Team appropriately uses the associated tools and processes.

The report contains no findings for corrective actions and five recommendations for continuous improvement as listed below.  Recommendations with an asterisk (*) are priority and should be tracked for closure.

1. Document the Risk Adjusted Estimate at Completion (RAEAC) value in
the NSF Monthly Report to comply with the NSF Major Facilities Guide
(MFG) for reporting risk exposure. Include a summary of the risk
analysis results with data tables and distribution curves whenever
the risk exposure (RAEAC) is updated.*
2. Perform a comprehensive Estimate at Completion (EAC) in conjunction
with the annual RAEAC analysis (as indicated by the MFG) and as a
precursor to the re-baseline.*
3. In Variance Analysis Reports (VARs) with multiple drivers, quantify
the cost and schedule impacts with each identified driver,
especially for VARs with both COVID and non-COVID related variances.*
4. Include both positive and negative cost and schedule variance
analysis reports in the NSF Monthly Reports per the MFG.*
5. Document the process for calculating total project risk exposure
from the aggregation of multiple independent WBS Level 2 Monte Carlo
simulations in either the Project Execution Plan (PEP), as a
supplement to the Risk Management Plan, or in a risk analysis report.

Please feel free to share the report with the ATLAS Project Team so they have the complete background on the recommendations.  I’m available to discuss any questions you and/or Columbia may have regarding this report.  I’ve placed a copy of this report in eJacket.

Best,

Rebecca

_______________________________________________________________________________

Rebecca Yasky, PE, PMP, CCM, EVP | NSF Large Facilities Office, 2415 Eisenhower Ave, Rm E 6323

Alexandria, VA  22314 | ryasky AT nsf.gov <mailto:ryasky AT nsf.gov> | 703-292-4309 (Office) | 757-254-2868 (Mobile)



Attachment: NSF HL-LHC ATLAS EVMS Surveillance Report Final 9-30-21.pdf
Description: Adobe PDF document

_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l


  • [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: ATLAS EVMS Surveillance Review Report, John Parsons, 10/04/2021

Archive powered by MHonArc 2.6.24.

Top of Page