usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List
List archive
[Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] May 2022 Status Sheets
- From: John Parsons <parsons AT nevis.columbia.edu>
- To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
- Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] May 2022 Status Sheets
- Date: Fri, 20 May 2022 10:54:03 -0400
It is status and technical bullets time again. Please take care of both by COB next Tuesday.
John
-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2l3ics-l] May 2022 Status Sheets
Date: Thu, 19 May 2022 15:08:01 +0000
From: Freedman, Rhoumela <rfreedman AT bnl.gov>
To: Usatlas-hllhc-l2l3ics-l AT lists.bnl.gov <usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>
Dear All,
*If you need help pleaseDO NOTreply to the mailing list*
**** The*/Pre-Status Reports/*//*/for May 2022/*have been uploaded in*DocDB 976*. These are the Gantt Charts for each subsystem. Please make sure to look over the chart while doing your Status Updates. ****
The UPDATED status sheets for the month of May are now available in google docs:
* *6.01 Pixels - *
https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1QKAGGY9G5bJkXZs45Wu167PAgrYB_26Kff5Kl312IJo/edit?usp=sharing__;!!P4SdNyxKAPE!Cjn29IdYoav9OYxJrtUXrpb2oNa-T16lHQjWQitdUGdbdBivSuqjxwQsE6GK9wCwymYzIMbTkKjNgCsXdUz5cQvCgjHIu798Snxdngu4Grm9oA$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1QKAGGY9G5bJkXZs45Wu167PAgrYB_26Kff5Kl312IJo/edit?usp=sharing__;!!P4SdNyxKAPE!Cjn29IdYoav9OYxJrtUXrpb2oNa-T16lHQjWQitdUGdbdBivSuqjxwQsE6GK9wCwymYzIMbTkKjNgCsXdUz5cQvCgjHIu798Snxdngu4Grm9oA$
>
* *6.02 Strips -
*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1oGXCBQNQnWBTmTkE_ji1YzoBi9pN9HCkyqg9QkyTYAc/edit?usp=sharing__;!!P4SdNyxKAPE!Cjn29IdYoav9OYxJrtUXrpb2oNa-T16lHQjWQitdUGdbdBivSuqjxwQsE6GK9wCwymYzIMbTkKjNgCsXdUz5cQvCgjHIu798SnxdngsIuzuVbQ$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1oGXCBQNQnWBTmTkE_ji1YzoBi9pN9HCkyqg9QkyTYAc/edit?usp=sharing__;!!P4SdNyxKAPE!Cjn29IdYoav9OYxJrtUXrpb2oNa-T16lHQjWQitdUGdbdBivSuqjxwQsE6GK9wCwymYzIMbTkKjNgCsXdUz5cQvCgjHIu798SnxdngsIuzuVbQ$
>
* *6.03 Global Mechanics -
*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1B_EHclks5sa8A89PCZzQKrgIPRWhzHR8vcnwCC7XgLs/edit?usp=sharing__;!!P4SdNyxKAPE!Cjn29IdYoav9OYxJrtUXrpb2oNa-T16lHQjWQitdUGdbdBivSuqjxwQsE6GK9wCwymYzIMbTkKjNgCsXdUz5cQvCgjHIu798SnxdngtDotqweA$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1B_EHclks5sa8A89PCZzQKrgIPRWhzHR8vcnwCC7XgLs/edit?usp=sharing__;!!P4SdNyxKAPE!Cjn29IdYoav9OYxJrtUXrpb2oNa-T16lHQjWQitdUGdbdBivSuqjxwQsE6GK9wCwymYzIMbTkKjNgCsXdUz5cQvCgjHIu798SnxdngtDotqweA$
>
* *6.04 LAr - *
https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1QwSRYLXRrU8cpI3ZKxa0-_aFTzGD-nTTfYA6FbiJ1FE/edit?usp=sharing__;!!P4SdNyxKAPE!Cjn29IdYoav9OYxJrtUXrpb2oNa-T16lHQjWQitdUGdbdBivSuqjxwQsE6GK9wCwymYzIMbTkKjNgCsXdUz5cQvCgjHIu798SnxdngsEChwL5A$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1QwSRYLXRrU8cpI3ZKxa0-_aFTzGD-nTTfYA6FbiJ1FE/edit?usp=sharing__;!!P4SdNyxKAPE!Cjn29IdYoav9OYxJrtUXrpb2oNa-T16lHQjWQitdUGdbdBivSuqjxwQsE6GK9wCwymYzIMbTkKjNgCsXdUz5cQvCgjHIu798SnxdngsEChwL5A$
>
* *6.05 Tiles -
*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1pbv97dEQ8siAR6X6h7TCZKf6t9TscV6Hjc-FrfodDiM/edit?usp=sharing__;!!P4SdNyxKAPE!Cjn29IdYoav9OYxJrtUXrpb2oNa-T16lHQjWQitdUGdbdBivSuqjxwQsE6GK9wCwymYzIMbTkKjNgCsXdUz5cQvCgjHIu798SnxdnguF01dhGQ$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1pbv97dEQ8siAR6X6h7TCZKf6t9TscV6Hjc-FrfodDiM/edit?usp=sharing__;!!P4SdNyxKAPE!Cjn29IdYoav9OYxJrtUXrpb2oNa-T16lHQjWQitdUGdbdBivSuqjxwQsE6GK9wCwymYzIMbTkKjNgCsXdUz5cQvCgjHIu798SnxdnguF01dhGQ$
>
* *6.06 Muons -
*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1CAonPDJp_Vdrhyg_RHVn71u0j0S0YoI0U8oaPEL17Z4/edit?usp=sharing__;!!P4SdNyxKAPE!Cjn29IdYoav9OYxJrtUXrpb2oNa-T16lHQjWQitdUGdbdBivSuqjxwQsE6GK9wCwymYzIMbTkKjNgCsXdUz5cQvCgjHIu798SnxdngsoGKC4LQ$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1CAonPDJp_Vdrhyg_RHVn71u0j0S0YoI0U8oaPEL17Z4/edit?usp=sharing__;!!P4SdNyxKAPE!Cjn29IdYoav9OYxJrtUXrpb2oNa-T16lHQjWQitdUGdbdBivSuqjxwQsE6GK9wCwymYzIMbTkKjNgCsXdUz5cQvCgjHIu798SnxdngsoGKC4LQ$
>
* *6.07 DAQ -
*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1svNOVCkU50byrDZm3nqXfuQ8jSGpsIU1TwlAACK8y7Y/edit?usp=sharing__;!!P4SdNyxKAPE!Cjn29IdYoav9OYxJrtUXrpb2oNa-T16lHQjWQitdUGdbdBivSuqjxwQsE6GK9wCwymYzIMbTkKjNgCsXdUz5cQvCgjHIu798SnxdnguFhmLY4w$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1svNOVCkU50byrDZm3nqXfuQ8jSGpsIU1TwlAACK8y7Y/edit?usp=sharing__;!!P4SdNyxKAPE!Cjn29IdYoav9OYxJrtUXrpb2oNa-T16lHQjWQitdUGdbdBivSuqjxwQsE6GK9wCwymYzIMbTkKjNgCsXdUz5cQvCgjHIu798SnxdnguFhmLY4w$
>
* *6.08 Trigger -
*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1cQ9qFaKi_sVxzit7JOPlZcapWHRGesEf5khEtf0uJQ8/edit?usp=sharing__;!!P4SdNyxKAPE!Cjn29IdYoav9OYxJrtUXrpb2oNa-T16lHQjWQitdUGdbdBivSuqjxwQsE6GK9wCwymYzIMbTkKjNgCsXdUz5cQvCgjHIu798Snxdngv_aExaKQ$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1cQ9qFaKi_sVxzit7JOPlZcapWHRGesEf5khEtf0uJQ8/edit?usp=sharing__;!!P4SdNyxKAPE!Cjn29IdYoav9OYxJrtUXrpb2oNa-T16lHQjWQitdUGdbdBivSuqjxwQsE6GK9wCwymYzIMbTkKjNgCsXdUz5cQvCgjHIu798Snxdngv_aExaKQ$
>
Please remember to update the status online –DO NOT downloadthe files.
The reports are at L2. The reports contain activities for May 2022-November 2022. You can filter for your CAM name in column D.
**** PLEASE NOTE THE FOLLOWING INSTRUCTIONS IN FILLING OUT YOUR STATUS SHEETS: ****
1. Please provide status in columns L, M, N, O, and S. Make sure that
for all activities in progress you provide **Expected Finish**
(column O). This is important for us to re-calculate the float and
the critical path.
2. The remaining units are calculated based on the original duration of
the activity and percent complete. We have added *column S*in which
we are asking you to update the **Units to Complete** based on your
experience and expectations. This is only in case you expect to
spend more or less labor for the specific activity or the cost for
material/travel is different than originally estimated. Column T
show Total Cost per resource from P6. Columns U (Remaining Cost
based on the remaining units from P6), V (Updated Remaining Cost,
also called ETC or Estimate-to-Complete), W (EAC or Estimate at
Complete, calculated based on updated units) and X (Delta EAC minus
baseline cost) are formula fields that provide calculations on how
the cost changes when the Remaining Units are adjusted.
3. Make sure that you enter the actual start date for all started
activities and finish date for all activities that are 100%
completed. All*_NEW_*actual start and finish dates*MUST BE*within
current reporting period.
4. Do*NOT*change the actual start/finish dates if they are already in
the spreadsheet – EVMS does not allow changing the past. If the
actual start date was entered incorrectly in the previous month just
leave it as it is.
5. Do*NOT*enter dates after May 31, 2022 in actual start/finish dates
(columns M and N) , this creates errors in P6.
6. Do*NOT*decrease percent complete in column L.
7. Do*NOT*write any notes in the spreadsheet, if you want to add a
comment use column Y.
8. Do*NOT*change the formatting of the cell once you edit it. The
spreadsheet will automatically highlight the change in yellow.
*_Additional Note: _*
If progress was made on future activities that are not in the status sheet you can contact your project controls specialist and ask for her help with statussing the activities directly in P6.
Please complete the February status update by*Thursday*,*May 26*.
We expect that the L2 managers and deputies will notify us (Penka, Carrie, Jenn, Rhoumela) as soon as the status for their system is complete.
Thank you,
Rhoumela
Rhoumela Freedman, Administrator
U.S. ATLAS HL-LHC Upgrade Project
Brookhaven National Laboratory, Physics Dept.
Tel: (631) 344-3460
Fax: (631) 344-6179
rfreedman AT bnl.gov <mailto:rfreedman AT bnl.gov>
<https://www.bnl.gov/>
Twitter <https://urldefense.com/v3/__https://twitter.com/BrookhavenLab__;!!P4SdNyxKAPE!Cjn29IdYoav9OYxJrtUXrpb2oNa-T16lHQjWQitdUGdbdBivSuqjxwQsE6GK9wCwymYzIMbTkKjNgCsXdUz5cQvCgjHIu798Snxdngv4p5d6MQ$ > | Facebook <https://urldefense.com/v3/__https://www.facebook.com/brookhavenlab__;!!P4SdNyxKAPE!Cjn29IdYoav9OYxJrtUXrpb2oNa-T16lHQjWQitdUGdbdBivSuqjxwQsE6GK9wCwymYzIMbTkKjNgCsXdUz5cQvCgjHIu798SnxdnguC1rin1g$ > | Instagram <https://urldefense.com/v3/__https://www.instagram.com/brookhavenlab/__;!!P4SdNyxKAPE!Cjn29IdYoav9OYxJrtUXrpb2oNa-T16lHQjWQitdUGdbdBivSuqjxwQsE6GK9wCwymYzIMbTkKjNgCsXdUz5cQvCgjHIu798SnxdngvUVOQKKA$ > | LinkedIn <https://urldefense.com/v3/__https://www.linkedin.com/company/brookhavenlab/__;!!P4SdNyxKAPE!Cjn29IdYoav9OYxJrtUXrpb2oNa-T16lHQjWQitdUGdbdBivSuqjxwQsE6GK9wCwymYzIMbTkKjNgCsXdUz5cQvCgjHIu798SnxdngssDXynag$ >
_______________________________________________
Usatlas-hllhc-l2l3ics-l mailing list
Usatlas-hllhc-l2l3ics-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2l3ics-l
- [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] May 2022 Status Sheets, John Parsons, 05/20/2022
Archive powered by MHonArc 2.6.24.