Skip to Content.
Sympa Menu

usatlas-hllhc-lartl2l3-l - [Usatlas-hllhc-lartl2l3-l] Fwd: ASIC projections

usatlas-hllhc-lartl2l3-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List

List archive

Chronological Thread  
  • From: Tim Andeen <timothy.robert.andeen AT cern.ch>
  • To: <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
  • Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: ASIC projections
  • Date: Fri, 17 Jun 2022 10:02:42 -0700

Hi all, 

Updated TSMC costs for this year for COLUTA and ALFE/HPS. Rumor is a 20% (or more) increase if we wait to January 2023. Gustaaf has budget codes assigned and has told me that the US PO will handle the payment processing when we’re invoiced by CERN. 

Best, Tim


__________________________________________________
Tim ANDEEN | Associate Professor | Department of Physics     
College of Natural Sciences | The University of Texas at Austin
tandeen AT utexas.edu | tandeen.web.cern.ch
office (TX) PMA 10.208 | (CERN)  304/1-024
ph (TX):  +1 512 475-9575 | (CERN): +41 (0)22 76 758 14
__________________________________________________


---------- Forwarded message ---------
From: Gustaaf Brooijmans <gustaaf.brooijmans AT cern.ch>
Date: Jun 16, 2022 at 11:08:10 AM
Subject: ASIC projections
To: Timothy Robert Andeen <timothy.robert.andeen AT cern.ch>, Nicolas Morange <nicolas.morange AT cern.ch>
Cc: menke AT mppmu.mpg.de <menke AT mppmu.mpg.de>



Here’s the sheet I forgot to send you…

Attachment: TSMC forecast 2022_03_25.ATLAS.LAr.v2.xlsx
Description: application/vnd.openxmlformats-officedocument.spreadsheetml.sheet



  • [Usatlas-hllhc-lartl2l3-l] Fwd: ASIC projections, Tim Andeen, 06/17/2022

Archive powered by MHonArc 2.6.24.

Top of Page