Skip to Content.
Sympa Menu

usatlas-hllhc-lartl2l3-l - [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF Quarterly Risk Workshop (Preparation for NSF re-baseline review)

usatlas-hllhc-lartl2l3-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List

List archive

Chronological Thread  
  • From: John Parsons <parsons AT nevis.columbia.edu>
  • To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
  • Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF Quarterly Risk Workshop (Preparation for NSF re-baseline review)
  • Date: Fri, 13 Jan 2023 12:35:43 -0500




-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF Quarterly Risk Workshop (Preparation for NSF re-baseline review)
Date: Thu, 12 Jan 2023 15:30:28 +0000
From: Meyer, Chris <cjmey AT iu.edu>
To: Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
CC: usatlas-hllhc-management-l AT lists.bnl.gov <usatlas-hllhc-management-l AT lists.bnl.gov>



Dear NSF L2s and Deputy L2s,

In preparation for the *NSF re-baseline review*, we will hold our quarterly *NSF risk workshop* during the CCB meeting on *Tuesday, January 31*. We will cover all systems in one meeting (~10 min per subsystem) and the agenda will be circulated soon.

As usual, please prepare slides covering:

* Changes in risks since the last risk review (especially those that
can be retired);
* Updated task affected (to make sure it remains in the future);
o In particular, *if you list multiple tasks affected* include a
clear description of how to treat this in the simulation. I.e.,
the risk should hit both tasks listed simultaneously (rare), or
a chain of tasks is listed as a reminder but only the first
should be considered in the simulation;
* Update comments to clearly describe how the cost/duration
uncertainties are arrived at;
* Potential changes to risks before the upcoming review, e.g.:
o changes to probability/impact of existing risks due to upcoming
technical reviews;
o existing risks that could be realized or that need to be watched
carefully;
o risks that might be retired.

The current risk register in docDB is v75, and the supply chain risk register is v7:

https://atlas-hllhc.docdb.bnl.gov/0001/000196/092/Risk-Register_v75.xlsx <https://atlas-hllhc.docdb.bnl.gov/0001/000196/092/Risk-Register_v75.xlsx>
https://atlas-hllhc.docdb.bnl.gov/0001/000196/092/Risk-Register_Supply-Chain_v7.xlsx <https://atlas-hllhc.docdb.bnl.gov/0001/000196/092/Risk-Register_Supply-Chain_v7.xlsx>

*Please look over both* in preparation for the workshop. After the workshop, please send Chris an updated version of the excel spreadsheet with your changes highlighted.

Any issues, please let us know.

    - Your friendly PO
_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l


  • [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF Quarterly Risk Workshop (Preparation for NSF re-baseline review), John Parsons, 01/13/2023

Archive powered by MHonArc 2.6.24.

Top of Page