Skip to Content.
Sympa Menu

usatlas-hllhc-lartl2l3-l - Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] April 2024 Status Sheets

usatlas-hllhc-lartl2l3-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List

List archive

Chronological Thread  
  • From: John Parsons <parsons AT nevis.columbia.edu>
  • To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
  • Subject: Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] April 2024 Status Sheets
  • Date: Thu, 25 Apr 2024 12:37:23 -0400


A further reminder; these are now overdue.

On 4/24/24 11:07 AM, John Parsons wrote:

A reminder that the status and technical bullets are due today (and thanks to Tim for doing it already).

        John

On 4/21/24 1:02 PM, John Parsons wrote:

Hi all,

     It is monthly status and technical bullets time again.  Please complete both by COB on Wednesday.

         John

-------- Forwarded Message --------
Subject:     [Usatlas-hllhc-l2l3ics-l] April 2024 Status Sheets
Date:     Thu, 18 Apr 2024 21:31:32 +0000
From:     Smith, Rosemarie <rsmith2 AT bnl.gov>
To:     Usatlas-hllhc-l2l3ics-l AT lists.bnl.gov <usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>



Good morning:

*If you need help, please DO NOT reply to the mailing list*

The Gantt Charts for each subsystem has been uploaded in *DocDB 976*. Please make sure to look over them while statussing the activities.

Status sheets for April 2024 are now available in google docs:

*Please note: The activities with baseline start dates in the past are highlighted in orange so you can see how this will impact your monthly performance.*

   * *6.01 Pixels: *

https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1uHDFXRxptj9oM3z8M3q7BIMphE-dRGhyLYeZm7zWMk0/edit?usp=sharing__;!!P4SdNyxKAPE!BZDOk5f12B4yqee0D2CqDPXDZFzqMCnXa2PVLIhhvY54Sz5OekUugRRDVHppmdVjZIhjuybbVwHb5ZD4UIWplf2YLBOCxfP-FRY3gK9CdYq4wQ$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1uHDFXRxptj9oM3z8M3q7BIMphE-dRGhyLYeZm7zWMk0/edit?usp=sharing__;!!P4SdNyxKAPE!BZDOk5f12B4yqee0D2CqDPXDZFzqMCnXa2PVLIhhvY54Sz5OekUugRRDVHppmdVjZIhjuybbVwHb5ZD4UIWplf2YLBOCxfP-FRY3gK9CdYq4wQ$
>

   * *6.02 Strips*:

https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1yoMBaVGOiWkma255p1plCTMuetSI7JzLpTPIG7gpgFA/edit?usp=sharing__;!!P4SdNyxKAPE!BZDOk5f12B4yqee0D2CqDPXDZFzqMCnXa2PVLIhhvY54Sz5OekUugRRDVHppmdVjZIhjuybbVwHb5ZD4UIWplf2YLBOCxfP-FRY3gK_1L6QZBg$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1yoMBaVGOiWkma255p1plCTMuetSI7JzLpTPIG7gpgFA/edit?usp=sharing__;!!P4SdNyxKAPE!BZDOk5f12B4yqee0D2CqDPXDZFzqMCnXa2PVLIhhvY54Sz5OekUugRRDVHppmdVjZIhjuybbVwHb5ZD4UIWplf2YLBOCxfP-FRY3gK_1L6QZBg$
>

   * *6.03 Global Mechanics: *

https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/10RT8mBA6LXf_ETRMpm2fwJ-E3CCJgDNFU6OS4KuDFjo/edit?usp=sharing__;!!P4SdNyxKAPE!BZDOk5f12B4yqee0D2CqDPXDZFzqMCnXa2PVLIhhvY54Sz5OekUugRRDVHppmdVjZIhjuybbVwHb5ZD4UIWplf2YLBOCxfP-FRY3gK-cl6-fCQ$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/10RT8mBA6LXf_ETRMpm2fwJ-E3CCJgDNFU6OS4KuDFjo/edit?usp=sharing__;!!P4SdNyxKAPE!BZDOk5f12B4yqee0D2CqDPXDZFzqMCnXa2PVLIhhvY54Sz5OekUugRRDVHppmdVjZIhjuybbVwHb5ZD4UIWplf2YLBOCxfP-FRY3gK-cl6-fCQ$
>

   * *6.04 Lar:*

https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1Gj_b0xs_zGsOKL6uSWy-XcjXHtt28GS3Qy-A_Yzf9Ug/edit?usp=sharing__;!!P4SdNyxKAPE!BZDOk5f12B4yqee0D2CqDPXDZFzqMCnXa2PVLIhhvY54Sz5OekUugRRDVHppmdVjZIhjuybbVwHb5ZD4UIWplf2YLBOCxfP-FRY3gK98PJWF7Q$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1Gj_b0xs_zGsOKL6uSWy-XcjXHtt28GS3Qy-A_Yzf9Ug/edit?usp=sharing__;!!P4SdNyxKAPE!BZDOk5f12B4yqee0D2CqDPXDZFzqMCnXa2PVLIhhvY54Sz5OekUugRRDVHppmdVjZIhjuybbVwHb5ZD4UIWplf2YLBOCxfP-FRY3gK98PJWF7Q$
>

   * *6.05 Tiles:*

https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1xudANKhh7yvgE2bpXbjZUbJHaZ-xNIyaeFXn7T_hHuM/edit?usp=sharing__;!!P4SdNyxKAPE!BZDOk5f12B4yqee0D2CqDPXDZFzqMCnXa2PVLIhhvY54Sz5OekUugRRDVHppmdVjZIhjuybbVwHb5ZD4UIWplf2YLBOCxfP-FRY3gK-1sn1gJg$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1xudANKhh7yvgE2bpXbjZUbJHaZ-xNIyaeFXn7T_hHuM/edit?usp=sharing__;!!P4SdNyxKAPE!BZDOk5f12B4yqee0D2CqDPXDZFzqMCnXa2PVLIhhvY54Sz5OekUugRRDVHppmdVjZIhjuybbVwHb5ZD4UIWplf2YLBOCxfP-FRY3gK-1sn1gJg$
>

   * *6.06 Muons:*

https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/18woAD-FrLjOWJZmgwgo9sYnJzyKl5obGUd6bi7KPBZM/edit?usp=sharing__;!!P4SdNyxKAPE!BZDOk5f12B4yqee0D2CqDPXDZFzqMCnXa2PVLIhhvY54Sz5OekUugRRDVHppmdVjZIhjuybbVwHb5ZD4UIWplf2YLBOCxfP-FRY3gK-299Bvag$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/18woAD-FrLjOWJZmgwgo9sYnJzyKl5obGUd6bi7KPBZM/edit?usp=sharing__;!!P4SdNyxKAPE!BZDOk5f12B4yqee0D2CqDPXDZFzqMCnXa2PVLIhhvY54Sz5OekUugRRDVHppmdVjZIhjuybbVwHb5ZD4UIWplf2YLBOCxfP-FRY3gK-299Bvag$
>

   * *6.07 DAQ: *

https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1fwe3LsmWU8O8Q5SBu_WHClv4tGXV1nyQs0Zx9QpL-tU/edit?usp=sharing__;!!P4SdNyxKAPE!BZDOk5f12B4yqee0D2CqDPXDZFzqMCnXa2PVLIhhvY54Sz5OekUugRRDVHppmdVjZIhjuybbVwHb5ZD4UIWplf2YLBOCxfP-FRY3gK-gOA3DMA$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1fwe3LsmWU8O8Q5SBu_WHClv4tGXV1nyQs0Zx9QpL-tU/edit?usp=sharing__;!!P4SdNyxKAPE!BZDOk5f12B4yqee0D2CqDPXDZFzqMCnXa2PVLIhhvY54Sz5OekUugRRDVHppmdVjZIhjuybbVwHb5ZD4UIWplf2YLBOCxfP-FRY3gK-gOA3DMA$
>

   * *6.08 Trigger: *

https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1c_j2EZm8MaaS3BD7BzcJ6viivBSGWWcYl8VAGS-TkY4/edit?usp=sharing__;!!P4SdNyxKAPE!BZDOk5f12B4yqee0D2CqDPXDZFzqMCnXa2PVLIhhvY54Sz5OekUugRRDVHppmdVjZIhjuybbVwHb5ZD4UIWplf2YLBOCxfP-FRY3gK92-61LDA$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1c_j2EZm8MaaS3BD7BzcJ6viivBSGWWcYl8VAGS-TkY4/edit?usp=sharing__;!!P4SdNyxKAPE!BZDOk5f12B4yqee0D2CqDPXDZFzqMCnXa2PVLIhhvY54Sz5OekUugRRDVHppmdVjZIhjuybbVwHb5ZD4UIWplf2YLBOCxfP-FRY3gK92-61LDA$
>

   * *6.11 Installation & Integration:*

https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/14shbtqHnbMxtvns4s9eRzq50LWLiASMoLAHdLyS3WKs/edit?usp=sharing__;!!P4SdNyxKAPE!BZDOk5f12B4yqee0D2CqDPXDZFzqMCnXa2PVLIhhvY54Sz5OekUugRRDVHppmdVjZIhjuybbVwHb5ZD4UIWplf2YLBOCxfP-FRY3gK_a03zN6w$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/14shbtqHnbMxtvns4s9eRzq50LWLiASMoLAHdLyS3WKs/edit?usp=sharing__;!!P4SdNyxKAPE!BZDOk5f12B4yqee0D2CqDPXDZFzqMCnXa2PVLIhhvY54Sz5OekUugRRDVHppmdVjZIhjuybbVwHb5ZD4UIWplf2YLBOCxfP-FRY3gK_a03zN6w$
>


Please remember to update the status online – DO NOT download the files.

The reports contain activities for April 2024 ~ September 2024. You can filter for your CAM name in column D.

**** PLEASE NOTE THE FOLLOWING INSTRUCTIONS IN FILLING OUT YOUR STATUS SHEETS: ****

  1. Please provide the status in columns L, M, N, O, and S. Make sure
     you provide the **Expected Finish** date (column O) for all
     *activities in progress*. This is important for us to re-calculate
     EAC, the float, and the critical path.
  2. The remaining units are calculated based on the original duration of
     the activity and the percent complete. Please provide **Units to
     Complete* in column S* for activities in progress. It is if you
     expect to use more or less labor for a specific task to be completed
     or the cost for material/travel is different than originally
     planned. Column T shows Total Cost per resource from P6. Columns U
     (Remaining Cost based on the remaining units from P6), V (Updated
     Remaining Cost, also called ETC or Estimate-to-Complete), W (EAC or
     Estimate at Complete, calculated based on updated units) and X
     (Delta EAC minus baseline cost) are formula fields that provide
     calculations on how the cost changes when the Remaining Units are
     adjusted.
  3. Make sure that you enter the actual start date for all started
     activities and finish date for all activities that are 100%
     completed. All *_NEW_* actual start and finish dates *MUST
     BE* within the current reporting period.
  4. Do *NOT *change the actual start dates if they are already in the
     spreadsheet – EVMS does not allow changing the past. If the actual
     start date was entered incorrectly in the previous month just leave
     it as it is.
  5. Do *NOT* enter dates after April 30, 2024,  in *actual* start/finish
     dates (columns M and N); this creates errors in P6.
  6. Do *NOT* decrease the percent complete in column L.
  7. Do *NOT* write any notes in the spreadsheet. If you want to add a
     comment use column Y.
  8. Do *NOT* change the formatting of the cell once you edit it.  The
     spreadsheet will automatically highlight the change in yellow.
*__*

*_Additional Note: _*

If progress was made on future activities that are not in the status sheet you can contact your project controls specialist and ask for her help with statussing the activities directly in P6.

Please complete the April Status updates by *_Friday, April 26^th _. *

We expect the L2 managers and deputies will notify Rosemarie, as soon as the status of their system is complete.

Thank you,

Rosemarie

Rosemarie D. Smith

U.S. ATLAS HL-LHC Upgrade Project

Brookhaven National Laboratory
Physics Department, Bldg. 510

PO Box 5000

Upton, NY 11973 -5000
Office: 631.344.3743
rsmith2 AT bnl.gov <mailto:rsmith2 AT bnl.gov>
cid:image001.png AT 01D88188.08BCB5B0
Twitter <https://urldefense.com/v3/__https://twitter.com/BrookhavenLab__;!!P4SdNyxKAPE!BZDOk5f12B4yqee0D2CqDPXDZFzqMCnXa2PVLIhhvY54Sz5OekUugRRDVHppmdVjZIhjuybbVwHb5ZD4UIWplf2YLBOCxfP-FRY3gK-feyHtJA$ > | Facebook <https://urldefense.com/v3/__https://www.facebook.com/brookhavenlab__;!!P4SdNyxKAPE!BZDOk5f12B4yqee0D2CqDPXDZFzqMCnXa2PVLIhhvY54Sz5OekUugRRDVHppmdVjZIhjuybbVwHb5ZD4UIWplf2YLBOCxfP-FRY3gK9fYCL3Dg$ > | Instagram <https://urldefense.com/v3/__https://www.instagram.com/brookhavenlab/__;!!P4SdNyxKAPE!BZDOk5f12B4yqee0D2CqDPXDZFzqMCnXa2PVLIhhvY54Sz5OekUugRRDVHppmdVjZIhjuybbVwHb5ZD4UIWplf2YLBOCxfP-FRY3gK9TciWjmQ$ > | LinkedIn <https://urldefense.com/v3/__https://www.linkedin.com/company/brookhavenlab/__;!!P4SdNyxKAPE!BZDOk5f12B4yqee0D2CqDPXDZFzqMCnXa2PVLIhhvY54Sz5OekUugRRDVHppmdVjZIhjuybbVwHb5ZD4UIWplf2YLBOCxfP-FRY3gK-VLf9gcw$ >

_______________________________________________
Usatlas-hllhc-lartl2l3-l mailing list
Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-lartl2l3-l


--
______________________________________________________________________

John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW:
https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!DwNATUtzULo8IjGPyW2HxQWv485CCmvmZ25N-ZpMlXczp3Wdult_5o9P58XFmHHFzjOo2UZVoBek7z5WP-y1eEHLdTAJ5NVMnF6PwiydDxh5Sg$


______________________________________________________________________




Archive powered by MHonArc 2.6.24.

Top of Page