- From: Timothy Robert Andeen <timothy.robert.andeen AT cern.ch>
- To: John Parsons <parsons AT nevis.columbia.edu>, "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
- Subject: Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] NSF CAMs design maturity scores
- Date: Wed, 15 May 2024 07:48:58 +0000
 
| 
Hi John,    Thanks for the reminder. I’ve reviewed and would like to keep everything the same, except for one task. In the google doc I’ve changed documentation at Austin to 1.15, in line with other documentation tasks
 at Columbia and SMU (ie correcting a mistake).    Best, Tim   
From:
Usatlas-hllhc-lartl2l3-l <usatlas-hllhc-lartl2l3-l-bounces AT lists.bnl.gov> on behalf of John Parsons <parsons AT nevis.columbia.edu>Date: Tuesday, May 14, 2024 at 6:01 PM
 To: usatlas-hllhc-lartl2l3-l AT lists.bnl.gov <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
 Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] NSF CAMs design maturity scores
 
Hi all,
 
 The NSF CAMS (Tim, Andy, me) need to update the maturity scores,
 according to the instructions from Penka below.  This is needed to run
 the MC in preparation for the July NSF annual review.  This update is
 now overdue, so please take care of it asap, and certainly before our
 meeting on Friday.  It should not take more than 15-30 minutes.
 Let me know when you are done it.
 Thanks,
 John
 
 -------- Forwarded Message --------
 Subject:         [Usatlas-hllhc-l2l3ics-l] NSF CAMs design maturity scores
 Date:    Thu, 2 May 2024 18:29:56 +0000
 From:    Novakova, Penka N <penka AT bnl.gov>
 To:      Usatlas-hllhc-l2l3ics-l AT lists.bnl.gov
 <usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>
 
 
 
 NSF CAMs,
 
 In preparation for the NSF annual review in July 2024 we need to update
 the design maturity (DM) scores in the P6 working schedule to be used
 for risk/DM simulation.
 
 Project controls team has prepared spreadsheets with DM scores, one tab
 per Control account (L3).
 
 * 6.04 Lar DM Score
 
 https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/14E4dOHL2f8vtaavsFDDnNvAM0zQtGrt0mp7sPmP1T90/edit?usp=sharing__;!!P4SdNyxKAPE!FFc3rnd8Qe9vgBJTWrZPgv5p2759-OOvzTs67MgDqoWdCKn871YsYuAtdFhxoRxsiohhxt2ETRXPdWTq9PsgazPYuyqE0MSw8otg50rNpy9kgA$
 
 <https://urldefense.com/v3/__https:/docs.google.com/spreadsheets/d/14E4dOHL2f8vtaavsFDDnNvAM0zQtGrt0mp7sPmP1T90/edit?usp=sharing__;!!P4SdNyxKAPE!FTEdCy1lZNktgUanm9ho2fvnWdQ1LmOH1Wk7tiGRB2k_l4PIRD5bZW8dgOG-viepXx_mARJS9e7W4tlHq50nYPE$>
 * 6.05 Tile DM Score
 
 https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/17S7ENKxRpjxigW6TkqZv6PBulK_ABQ0hfFcoygYLBRk/edit?usp=sharing__;!!P4SdNyxKAPE!FFc3rnd8Qe9vgBJTWrZPgv5p2759-OOvzTs67MgDqoWdCKn871YsYuAtdFhxoRxsiohhxt2ETRXPdWTq9PsgazPYuyqE0MSw8otg50oLUz26Xw$
 
 <https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/17S7ENKxRpjxigW6TkqZv6PBulK_ABQ0hfFcoygYLBRk/edit?usp=sharing__;!!P4SdNyxKAPE!FFc3rnd8Qe9vgBJTWrZPgv5p2759-OOvzTs67MgDqoWdCKn871YsYuAtdFhxoRxsiohhxt2ETRXPdWTq9PsgazPYuyqE0MSw8otg50oLUz26Xw$
 >
 * 6.06 Muon DM Score
 
 https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1NfbzZYQ4fMlRkbeszNx5JtUg3sQg5SD6druNrd8WfuA/edit?usp=sharing__;!!P4SdNyxKAPE!FFc3rnd8Qe9vgBJTWrZPgv5p2759-OOvzTs67MgDqoWdCKn871YsYuAtdFhxoRxsiohhxt2ETRXPdWTq9PsgazPYuyqE0MSw8otg50qzbS7f2A$
 
 <https://urldefense.com/v3/__https:/docs.google.com/spreadsheets/d/1NfbzZYQ4fMlRkbeszNx5JtUg3sQg5SD6druNrd8WfuA/edit?usp=sharing__;!!P4SdNyxKAPE!FTEdCy1lZNktgUanm9ho2fvnWdQ1LmOH1Wk7tiGRB2k_l4PIRD5bZW8dgOG-viepXx_mARJS9e7W4tlH0GibfNo$>
 
 * 6.08 Trigger DM Score
 
 https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1tLMyQXiLwm-FatzxEb0P-GnAomYADbshJbob67xAzDQ/edit?usp=sharing__;!!P4SdNyxKAPE!FFc3rnd8Qe9vgBJTWrZPgv5p2759-OOvzTs67MgDqoWdCKn871YsYuAtdFhxoRxsiohhxt2ETRXPdWTq9PsgazPYuyqE0MSw8otg50okAO6zKg$
 
 <https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1tLMyQXiLwm-FatzxEb0P-GnAomYADbshJbob67xAzDQ/edit?usp=sharing__;!!P4SdNyxKAPE!FFc3rnd8Qe9vgBJTWrZPgv5p2759-OOvzTs67MgDqoWdCKn871YsYuAtdFhxoRxsiohhxt2ETRXPdWTq9PsgazPYuyqE0MSw8otg50okAO6zKg$
 >
 
 I have attached the estimate uncertainty rules, also available in docdb 75.
 
 Please update the DM scores in column I, if needed, by Thursday, May 9.
 
 Thank you,
 
 Penka
 