Hi John,
Status updated and bullets below.
ADC
- Production wafers arrived at CERN. Arranging shipment to packager.
- PRR scheduling planned for June.
- Packager (JCET) contacted and ready. Requesting to package the additional engineering run wafers and 2 wafers from each of the 2 production lots (before PRR).
- Robotic test-stand (RTS) integration work ongoing and soft-walled clean room deployed and in use.
- Mass test boards at Austin integrated in robotic setup. Repeatability of testing studies showed initial issues with repeatability. Board and firmware debugging has made significant improvements. Investigating
socket as possible source of issue. Good performance with combination of clean room, socket cleaning, and now identifying the precise source of the improvement.
- Coordination with Saclay on QC parameters ongoing, discussions continue as we understand the test setup reliability.
OPTICS:
- Investigating measurements of spectrum of light emitted by VTRx during QC testing. With firefly in lab considering two setups, one with data-only links to splitter to test with optical spec. analyzer and a second
testing the control links, similar setup. Evaluating purchase of optical spectrum analyzer.
- Initial batch of 345 VTRx+ delivered from CERN and under test.
- Control code in development.
- Student testers hired, and training ongoing.
- Fiber placement on board under study. Discussions with FEB2 designers on exact placement of fiber saddles, holes for saddles and connectors, with modules in the lab with 37 cm pigtails attached. Placement scheme
agreed on.
From:
Usatlas-hllhc-lartl2l3-l <usatlas-hllhc-lartl2l3-l-bounces AT lists.bnl.gov> on behalf of John Parsons <parsons AT nevis.columbia.edu>
Date: Monday, May 20, 2024 at 5:50 PM
To: usatlas-hllhc-lartl2l3-l AT lists.bnl.gov <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] May 2024 Status Sheets
Hi all,
It is status and technical bullets time again. Please complete both
before our meeting on Friday.
Thanks,
John
-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2l3ics-l] May 2024 Status Sheets
Date: Mon, 20 May 2024 14:58:06 +0000
From: Smith, Rosemarie <rsmith2 AT bnl.gov>
To: Usatlas-hllhc-l2l3ics-l AT lists.bnl.gov
<usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>
Good morning,
*If you need help, please DO NOT reply to the mailing list*
The Gantt Charts for each subsystem has been uploaded in *DocDB 976*.
Please make sure to look over them while statussing the activities.
Status sheets for May 2024 are now available in google docs:
*Please note: The activities with baseline start dates in the past are
highlighted in orange so you can see how this will impact your monthly
performance.***
* *6.01 Pixels:
*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/10vYRsYJYdiXyOs9GyAzzqWP2OdMDEEeH8ttbtnPFLXs/edit?usp=sharing__;!!P4SdNyxKAPE!FTlmUxpcbp8fUAq8FcEzarpVsw9MhwFnUJrwcAMgcqWznwLP9yeIcSxNTlFXkiC6PoxocwFjfLtEn0IF9BSjxMop4MM5de0POVjO5yDgS6466Q$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/10vYRsYJYdiXyOs9GyAzzqWP2OdMDEEeH8ttbtnPFLXs/edit?usp=sharing__;!!P4SdNyxKAPE!FTlmUxpcbp8fUAq8FcEzarpVsw9MhwFnUJrwcAMgcqWznwLP9yeIcSxNTlFXkiC6PoxocwFjfLtEn0IF9BSjxMop4MM5de0POVjO5yDgS6466Q$
>
* *6.02 Strips*:
https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1-flOiD6PrHlIWhvjB2bF0IRS1ELHot20APVuhKPEARI/edit?usp=sharing__;!!P4SdNyxKAPE!FTlmUxpcbp8fUAq8FcEzarpVsw9MhwFnUJrwcAMgcqWznwLP9yeIcSxNTlFXkiC6PoxocwFjfLtEn0IF9BSjxMop4MM5de0POVjO5yCxhoVCAw$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1-flOiD6PrHlIWhvjB2bF0IRS1ELHot20APVuhKPEARI/edit?usp=sharing__;!!P4SdNyxKAPE!FTlmUxpcbp8fUAq8FcEzarpVsw9MhwFnUJrwcAMgcqWznwLP9yeIcSxNTlFXkiC6PoxocwFjfLtEn0IF9BSjxMop4MM5de0POVjO5yCxhoVCAw$
>
* *6.03 Global Mechanics:
*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/11zWpQcP_DjHVfpK3QfPGQxvBMXS5gA55YGI5-CX8FIE/edit?usp=sharing__;!!P4SdNyxKAPE!FTlmUxpcbp8fUAq8FcEzarpVsw9MhwFnUJrwcAMgcqWznwLP9yeIcSxNTlFXkiC6PoxocwFjfLtEn0IF9BSjxMop4MM5de0POVjO5yAx6RvynQ$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/11zWpQcP_DjHVfpK3QfPGQxvBMXS5gA55YGI5-CX8FIE/edit?usp=sharing__;!!P4SdNyxKAPE!FTlmUxpcbp8fUAq8FcEzarpVsw9MhwFnUJrwcAMgcqWznwLP9yeIcSxNTlFXkiC6PoxocwFjfLtEn0IF9BSjxMop4MM5de0POVjO5yAx6RvynQ$
>
* *6.04
Lar:*https://docs.google.com/spreadsheets/d/1L7znnUYOBAoN6WUyRYcXBJkeur-mllMs1Ylef7OFZ3c/edit?usp=sharing
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1L7znnUYOBAoN6WUyRYcXBJkeur-mllMs1Ylef7OFZ3c/edit?usp=sharing__;!!P4SdNyxKAPE!FTlmUxpcbp8fUAq8FcEzarpVsw9MhwFnUJrwcAMgcqWznwLP9yeIcSxNTlFXkiC6PoxocwFjfLtEn0IF9BSjxMop4MM5de0POVjO5yDPevmDNg$
>
* *6.05
Tiles:*https://docs.google.com/spreadsheets/d/15mtVqSWPeq0JIKg1Qpo_HYOZMsmIEgoFjLLP6Ko_wn0/edit?usp=sharing
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/15mtVqSWPeq0JIKg1Qpo_HYOZMsmIEgoFjLLP6Ko_wn0/edit?usp=sharing__;!!P4SdNyxKAPE!FTlmUxpcbp8fUAq8FcEzarpVsw9MhwFnUJrwcAMgcqWznwLP9yeIcSxNTlFXkiC6PoxocwFjfLtEn0IF9BSjxMop4MM5de0POVjO5yBDPf-jsg$
>
* *6.06
Muons:*https://docs.google.com/spreadsheets/d/1_T1hK5ZhBfQtm29GGes3H-bsr9ynnxVD05mGmEv8dUQ/edit?usp=sharing
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1_T1hK5ZhBfQtm29GGes3H-bsr9ynnxVD05mGmEv8dUQ/edit?usp=sharing__;!!P4SdNyxKAPE!FTlmUxpcbp8fUAq8FcEzarpVsw9MhwFnUJrwcAMgcqWznwLP9yeIcSxNTlFXkiC6PoxocwFjfLtEn0IF9BSjxMop4MM5de0POVjO5yAVL70D4A$
>
* *6.07 DAQ:
*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1J0ElXuLo6D6uVpyWEE7U1xWFoD72Q9DuGjjs_pItmHk/edit?usp=sharing__;!!P4SdNyxKAPE!FTlmUxpcbp8fUAq8FcEzarpVsw9MhwFnUJrwcAMgcqWznwLP9yeIcSxNTlFXkiC6PoxocwFjfLtEn0IF9BSjxMop4MM5de0POVjO5yAM5SXzWw$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1J0ElXuLo6D6uVpyWEE7U1xWFoD72Q9DuGjjs_pItmHk/edit?usp=sharing__;!!P4SdNyxKAPE!FTlmUxpcbp8fUAq8FcEzarpVsw9MhwFnUJrwcAMgcqWznwLP9yeIcSxNTlFXkiC6PoxocwFjfLtEn0IF9BSjxMop4MM5de0POVjO5yAM5SXzWw$
>
* *6.08 Trigger:
*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1ELlfQRW1rMXs3BjiIUmHJEwAqKbCRKuY9Nk6bWjNATI/edit?usp=sharing__;!!P4SdNyxKAPE!FTlmUxpcbp8fUAq8FcEzarpVsw9MhwFnUJrwcAMgcqWznwLP9yeIcSxNTlFXkiC6PoxocwFjfLtEn0IF9BSjxMop4MM5de0POVjO5yA6BiJEsg$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1ELlfQRW1rMXs3BjiIUmHJEwAqKbCRKuY9Nk6bWjNATI/edit?usp=sharing__;!!P4SdNyxKAPE!FTlmUxpcbp8fUAq8FcEzarpVsw9MhwFnUJrwcAMgcqWznwLP9yeIcSxNTlFXkiC6PoxocwFjfLtEn0IF9BSjxMop4MM5de0POVjO5yA6BiJEsg$
>
* *6.11 Installation &
Integration:*https://docs.google.com/spreadsheets/d/1H2iX9hfZ-dJh4GW103ozmQGrWBbIpbuFJfLN2N-0tC8/edit?usp=sharing
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1H2iX9hfZ-dJh4GW103ozmQGrWBbIpbuFJfLN2N-0tC8/edit?usp=sharing__;!!P4SdNyxKAPE!FTlmUxpcbp8fUAq8FcEzarpVsw9MhwFnUJrwcAMgcqWznwLP9yeIcSxNTlFXkiC6PoxocwFjfLtEn0IF9BSjxMop4MM5de0POVjO5yAeEGQHKw$
>
Please remember to update the status online – DO NOT download the files.
The reports contain activities for May 2024 ~ October 2024. You can
filter for your CAM name in column D.
**** PLEASE NOTE THE FOLLOWING INSTRUCTIONS IN FILLING OUT YOUR STATUS
SHEETS: ****
1. Please provide the status in columns L, M, N, O, and S. Make sure
you provide the **Expected Finish** date (column O) for all
*activities in progress*. This is important for us to re-calculate
EAC, the float, and the critical path.
2. The remaining units are calculated based on the original duration of
the activity and the percent complete. Please provide **Units to
Complete* in column S* for activities in progress. It is if you
expect to use more or less labor for a specific task to be completed
or the cost for material/travel is different than originally
planned. Column T shows Total Cost per resource from P6. Columns U
(Remaining Cost based on the remaining units from P6), V (Updated
Remaining Cost, also called ETC or Estimate-to-Complete), W (EAC or
Estimate at Complete, calculated based on updated units) and X
(Delta EAC minus baseline cost) are formula fields that provide
calculations on how the cost changes when the Remaining Units are
adjusted.
3. Make sure that you enter the actual start date for all started
activities and finish date for all activities that are 100%
completed. All *_NEW_* actual start and finish dates *MUST
BE* within the current reporting period.
4. Do *NOT *change the actual start dates if they are already in the
spreadsheet – EVMS does not allow changing the past. If the actual
start date was entered incorrectly in the previous month just leave
it as it is.
5. Do *NOT* enter dates after May 31, 2024, in *actual* start/finish
dates (columns M and N); this creates errors in P6.
6. Do *NOT* decrease the percent complete in column L.
7. Do *NOT* write any notes in the spreadsheet. If you want to add a
comment use column Y.
8. Do *NOT* change the formatting of the cell once you edit it. The
spreadsheet will automatically highlight the change in yellow.
*__*
*_Additional Note: _*
If progress was made on future activities that are not in the status
sheet you can contact your project controls specialist and ask for her
help with statussing the activities directly in P6.
Please complete the May Status updates by *_Tuesday, May 28^th _. *
We expect the L2 managers and deputies will notify Rosemarie, as soon as
the status of their system is complete.
Thank you,
Rosemarie
Rosemarie D. Smith
U.S. ATLAS HL-LHC Upgrade Project
Brookhaven National Laboratory
Physics Department, Bldg. 510
PO Box 5000
Upton, NY 11973 -5000
Office: 631.344.3743
rsmith2 AT bnl.gov <mailto:rsmith2 AT bnl.gov>
Twitter <https://urldefense.com/v3/__https://twitter.com/BrookhavenLab__;!!P4SdNyxKAPE!FTlmUxpcbp8fUAq8FcEzarpVsw9MhwFnUJrwcAMgcqWznwLP9yeIcSxNTlFXkiC6PoxocwFjfLtEn0IF9BSjxMop4MM5de0POVjO5yAnayvNmg$ > | Facebook
<https://urldefense.com/v3/__https://www.facebook.com/brookhavenlab__;!!P4SdNyxKAPE!FTlmUxpcbp8fUAq8FcEzarpVsw9MhwFnUJrwcAMgcqWznwLP9yeIcSxNTlFXkiC6PoxocwFjfLtEn0IF9BSjxMop4MM5de0POVjO5yCshUkcTg$ > | Instagram
<https://urldefense.com/v3/__https://www.instagram.com/brookhavenlab/__;!!P4SdNyxKAPE!FTlmUxpcbp8fUAq8FcEzarpVsw9MhwFnUJrwcAMgcqWznwLP9yeIcSxNTlFXkiC6PoxocwFjfLtEn0IF9BSjxMop4MM5de0POVjO5yBGtMA3KQ$ > | LinkedIn
<https://urldefense.com/v3/__https://www.linkedin.com/company/brookhavenlab/__;!!P4SdNyxKAPE!FTlmUxpcbp8fUAq8FcEzarpVsw9MhwFnUJrwcAMgcqWznwLP9yeIcSxNTlFXkiC6PoxocwFjfLtEn0IF9BSjxMop4MM5de0POVjO5yACUbovrA$ >
|