  • From: John Parsons <parsons AT nevis.columbia.edu>
  • To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
  • Subject: [[Usatlas-hllhc-lartl2l3-l] ] Fwd: [[Usatlas-hllhc-l2l3ics-l] ] [Usatlas-hllhc-l2l3ics-l] FY25 October 2024 Status Sheets
  • Date: Mon, 21 Oct 2024 13:26:24 -0400


Hi all,

It is tech bullets and status time again. Please take care of both by this Friday at the latest.
Thanks,
John

-------- Forwarded Message --------
Subject: [[Usatlas-hllhc-l2l3ics-l] ] [Usatlas-hllhc-l2l3ics-l] FY25 October 2024 Status Sheets
Date: Mon, 21 Oct 2024 16:46:16 +0000
From: Smith, Rosemarie <rsmith2 AT bnl.gov>
Reply-To: Smith, Rosemarie <rsmith2 AT bnl.gov>
To: Usatlas-hllhc-l2l3ics-l AT lists.bnl.gov <usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>



Good Afternoon:

*If you need help, please*DO NOT* reply to the /mailing list/*

The Gantt Charts for each subsystem has been uploaded in *DocDB 976*. Please make sure to look over them while statussing the activities.

The Status sheets for October 2024 are now available in google docs:

                              Please note: The activities with baseline start dates in the past are highlighted in orange so you can see how this impact your monthly performance.

* *6.01 Pixels:
*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1HC51MnomEFW4aL1H2ClusQyA4N7tm1goWLAxk7SoNLg/edit?usp=sharing__;!!P4SdNyxKAPE!GaPutVw0UzLah967E-5cJFNLvEjkLZcdlCH2vR26Knbdq3EOeQuB6EovekvlY5EaxRJqVuCsPkhYRqZLZN5bd3w3Vpeksp61f4q3JeY2iXQG2w$ <https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1HC51MnomEFW4aL1H2ClusQyA4N7tm1goWLAxk7SoNLg/edit?usp=sharing__;!!P4SdNyxKAPE!GaPutVw0UzLah967E-5cJFNLvEjkLZcdlCH2vR26Knbdq3EOeQuB6EovekvlY5EaxRJqVuCsPkhYRqZLZN5bd3w3Vpeksp61f4q3JeY2iXQG2w$ >**
* *6.02 Strips:
*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1h0pDEpFx83gMyTKJvFNF_2hAq-3PcFmDflr0EMRAG2I/edit?usp=sharing__;!!P4SdNyxKAPE!GaPutVw0UzLah967E-5cJFNLvEjkLZcdlCH2vR26Knbdq3EOeQuB6EovekvlY5EaxRJqVuCsPkhYRqZLZN5bd3w3Vpeksp61f4q3Jea_fbhzEw$ <https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1h0pDEpFx83gMyTKJvFNF_2hAq-3PcFmDflr0EMRAG2I/edit?usp=sharing__;!!P4SdNyxKAPE!GaPutVw0UzLah967E-5cJFNLvEjkLZcdlCH2vR26Knbdq3EOeQuB6EovekvlY5EaxRJqVuCsPkhYRqZLZN5bd3w3Vpeksp61f4q3Jea_fbhzEw$ >**
* *6.03 Global Mechanics:
*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/172qgp1eMdU20qgx1wvcyemmLIEJFbfQicF8p62_6hbc/edit?usp=sharing__;!!P4SdNyxKAPE!GaPutVw0UzLah967E-5cJFNLvEjkLZcdlCH2vR26Knbdq3EOeQuB6EovekvlY5EaxRJqVuCsPkhYRqZLZN5bd3w3Vpeksp61f4q3JeZsszdKng$ <https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/172qgp1eMdU20qgx1wvcyemmLIEJFbfQicF8p62_6hbc/edit?usp=sharing__;!!P4SdNyxKAPE!GaPutVw0UzLah967E-5cJFNLvEjkLZcdlCH2vR26Knbdq3EOeQuB6EovekvlY5EaxRJqVuCsPkhYRqZLZN5bd3w3Vpeksp61f4q3JeZsszdKng$ >**
* *6.04 LAr:
*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/13T3KKA_zp1zv9lbVRy67ZWSP1B9xDrrjN0kHVBMOGro/edit?usp=sharing__;!!P4SdNyxKAPE!GaPutVw0UzLah967E-5cJFNLvEjkLZcdlCH2vR26Knbdq3EOeQuB6EovekvlY5EaxRJqVuCsPkhYRqZLZN5bd3w3Vpeksp61f4q3JeZT69Gj7g$ <https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/13T3KKA_zp1zv9lbVRy67ZWSP1B9xDrrjN0kHVBMOGro/edit?usp=sharing__;!!P4SdNyxKAPE!GaPutVw0UzLah967E-5cJFNLvEjkLZcdlCH2vR26Knbdq3EOeQuB6EovekvlY5EaxRJqVuCsPkhYRqZLZN5bd3w3Vpeksp61f4q3JeZT69Gj7g$ >**
* *6.05 Tiles:
*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1AoqvR85mm1sRdNiHX7He8NNYHIioQIemyYhci-Df3Gk/edit?usp=sharing__;!!P4SdNyxKAPE!GaPutVw0UzLah967E-5cJFNLvEjkLZcdlCH2vR26Knbdq3EOeQuB6EovekvlY5EaxRJqVuCsPkhYRqZLZN5bd3w3Vpeksp61f4q3JebQmhBP7g$ <https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1AoqvR85mm1sRdNiHX7He8NNYHIioQIemyYhci-Df3Gk/edit?usp=sharing__;!!P4SdNyxKAPE!GaPutVw0UzLah967E-5cJFNLvEjkLZcdlCH2vR26Knbdq3EOeQuB6EovekvlY5EaxRJqVuCsPkhYRqZLZN5bd3w3Vpeksp61f4q3JebQmhBP7g$ >**
* *6.06 Muon:
*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1_xCMzUhk2wVImCH7AO1Cx13faH0rTiJrKfqhK1ehxNg/edit?usp=sharing__;!!P4SdNyxKAPE!GaPutVw0UzLah967E-5cJFNLvEjkLZcdlCH2vR26Knbdq3EOeQuB6EovekvlY5EaxRJqVuCsPkhYRqZLZN5bd3w3Vpeksp61f4q3JeaubfbRmg$ <https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1_xCMzUhk2wVImCH7AO1Cx13faH0rTiJrKfqhK1ehxNg/edit?usp=sharing__;!!P4SdNyxKAPE!GaPutVw0UzLah967E-5cJFNLvEjkLZcdlCH2vR26Knbdq3EOeQuB6EovekvlY5EaxRJqVuCsPkhYRqZLZN5bd3w3Vpeksp61f4q3JeaubfbRmg$ >**
* *6.07 DAQ:
*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1WMqYR7QhAKg-uGagVUZ8beGt1-3Zxp-m6xGajJ4nnOI/edit?usp=sharing__;!!P4SdNyxKAPE!GaPutVw0UzLah967E-5cJFNLvEjkLZcdlCH2vR26Knbdq3EOeQuB6EovekvlY5EaxRJqVuCsPkhYRqZLZN5bd3w3Vpeksp61f4q3JeYETEVuGA$ <https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1WMqYR7QhAKg-uGagVUZ8beGt1-3Zxp-m6xGajJ4nnOI/edit?usp=sharing__;!!P4SdNyxKAPE!GaPutVw0UzLah967E-5cJFNLvEjkLZcdlCH2vR26Knbdq3EOeQuB6EovekvlY5EaxRJqVuCsPkhYRqZLZN5bd3w3Vpeksp61f4q3JeYETEVuGA$ >**
* *6.08 Trigger:
*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/17Tph6wJs_VQ2vg-HnSb6z8QV3uTHiMW2grcBYe77qZU/edit?usp=sharing__;!!P4SdNyxKAPE!GaPutVw0UzLah967E-5cJFNLvEjkLZcdlCH2vR26Knbdq3EOeQuB6EovekvlY5EaxRJqVuCsPkhYRqZLZN5bd3w3Vpeksp61f4q3JeYU5UrKdQ$ <https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/17Tph6wJs_VQ2vg-HnSb6z8QV3uTHiMW2grcBYe77qZU/edit?usp=sharing__;!!P4SdNyxKAPE!GaPutVw0UzLah967E-5cJFNLvEjkLZcdlCH2vR26Knbdq3EOeQuB6EovekvlY5EaxRJqVuCsPkhYRqZLZN5bd3w3Vpeksp61f4q3JeYU5UrKdQ$ >**
* *6.11 Installation & Integration:
*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1j4uBKqjJcZBQMtOZzHP-B6fO_bpHCuo6TBJ6JY47nVY/edit?usp=sharing__;!!P4SdNyxKAPE!GaPutVw0UzLah967E-5cJFNLvEjkLZcdlCH2vR26Knbdq3EOeQuB6EovekvlY5EaxRJqVuCsPkhYRqZLZN5bd3w3Vpeksp61f4q3JeYJtM7fZg$ <https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1j4uBKqjJcZBQMtOZzHP-B6fO_bpHCuo6TBJ6JY47nVY/edit?usp=sharing__;!!P4SdNyxKAPE!GaPutVw0UzLah967E-5cJFNLvEjkLZcdlCH2vR26Knbdq3EOeQuB6EovekvlY5EaxRJqVuCsPkhYRqZLZN5bd3w3Vpeksp61f4q3JeYJtM7fZg$ >**

**

Please remember to update the status online – *_DO NOT_* Download the files.

The reports contain activities for *October 2024 ~ March 2025*. You can filter for your CAM’s name within column D.

***PLEASE NOTE THE FOLLOWING INSTRUCTIONS IN FILLING OUT THE STATUS SHEETS:***

1. Please provide the status in columns: *L, M, N, O, and S*. Make sure
you provide the “*Expected Finish*” date(column *O*) for all
activities in progress. This is important for us to re-calculate
EAC, the float, and the critical path.
2. The remaining units are calculated based on the original duration of
the activity and the percentage completed. Please provide “*Units to
Complete*” (column *S*) for activities in progress. It is if you
expect to use more or less labor for a specific task to be completed
or the cost for material/travel is different than originally
planned. Total Cost per resource from P6, is shown in column *T
*(“*Planned Cost*”). The “*Remaining Cost*” (based on the remaining
units from P6), is in column *U*; the “*Updated Remaining Cost*”
(column *V*), also called: ETC or Estimate-to-Complete); the
“*Updated Total Cost*” (column *W*) also called: (EAC or Estimate at
Complete, calculated based on updated units); and the *Delta EAC
minus baseline cost* (column *X*); are formula fields that provide
calculations on how the cost changes when the Remaining Units are
adjusted.
3. Make sure that you enter the actual start date for all started
activities and finish date for all activities that are 100%
completed. All *_NEW_* actual start and finish dates *_MUST BE_*
within the current reporting period.
4. Do *NOT* change the actual start dates if they are already in the
spreadsheet – EVMS does not allow changing the past. If the actual
start date was entered incorrectly in the previous month, just leave
it as it is.
5. Do *NOT* enter dates after *_October 31, 2024_*, in actual
start/finish dates (columns *M* and *N*); this creates errors in P6.
6. Do *NOT* decrease the percentage complete in column *L*.
7. Do *NOT* write any notes in the spreadsheet. If you want to add a
comment use column *Y*.
8. Do *NOT* change the formatting of the cell once you edit it. The
spreadsheet will automatically highlight the change in *YELLOW*.

*_Additional Note_*:

If progress was made on future activities that are not in the status sheet, you can contact your project controls specialist and ask for their help with statussing the activities directly in P6.

*PLEASE Complete the October Status update**_by Monday, October 28^th MORNING_*.

*We expect the L2 managers and deputies will notify Rosemarie as soon as the status of their system is complete*.

Thank you,

*Rosemarie*

Rosemarie D. Smith

U.S. ATLAS HL-LHC Upgrade Project

Brookhaven National Laboratory
Physics Department, Bldg. 510

PO Box 5000

Upton, NY 11973 -5000
Office: 631.344.3743
rsmith2 AT bnl.gov <mailto:rsmith2 AT bnl.gov>

Twitter <https://urldefense.com/v3/__https://twitter.com/BrookhavenLab__;!!P4SdNyxKAPE!GaPutVw0UzLah967E-5cJFNLvEjkLZcdlCH2vR26Knbdq3EOeQuB6EovekvlY5EaxRJqVuCsPkhYRqZLZN5bd3w3Vpeksp61f4q3Jea-qI87uw$ > | Facebook <https://urldefense.com/v3/__https://www.facebook.com/brookhavenlab__;!!P4SdNyxKAPE!GaPutVw0UzLah967E-5cJFNLvEjkLZcdlCH2vR26Knbdq3EOeQuB6EovekvlY5EaxRJqVuCsPkhYRqZLZN5bd3w3Vpeksp61f4q3JebnobHnpg$ > | Instagram <https://urldefense.com/v3/__https://www.instagram.com/brookhavenlab/__;!!P4SdNyxKAPE!GaPutVw0UzLah967E-5cJFNLvEjkLZcdlCH2vR26Knbdq3EOeQuB6EovekvlY5EaxRJqVuCsPkhYRqZLZN5bd3w3Vpeksp61f4q3JeYL1s9tqQ$ > | LinkedIn <https://urldefense.com/v3/__https://www.linkedin.com/company/brookhavenlab/__;!!P4SdNyxKAPE!GaPutVw0UzLah967E-5cJFNLvEjkLZcdlCH2vR26Knbdq3EOeQuB6EovekvlY5EaxRJqVuCsPkhYRqZLZN5bd3w3Vpeksp61f4q3Jebv2570Cw$ >



  • [[Usatlas-hllhc-lartl2l3-l] ] Fwd: [[Usatlas-hllhc-l2l3ics-l] ] [Usatlas-hllhc-l2l3ics-l] FY25 October 2024 Status Sheets, John Parsons, 10/21/2024

Archive powered by MHonArc 2.6.24.

Top of Page