I will be on vacation from Nov 23 to Dec 2. So we need to prepare this next week.
I will work with Hao on that.
Best,
Hong.
From:
usatlas-hllhc-lartl2l3-l-request AT lists.bnl.gov <usatlas-hllhc-lartl2l3-l-request AT lists.bnl.gov> on behalf of John Parsons <parsons AT nevis.columbia.edu>
Date: Thursday, November 14, 2024 at 9:11 AM
To: usatlas-hllhc-lartl2l3-l AT lists.bnl.gov <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
Subject: [[Usatlas-hllhc-lartl2l3-l] ] Fwd: [[Usatlas-hllhc-l2deputymgmt-doe-l] ] DOE Risk workshop Dec 3
FYI Hong and Hao.
-------- Forwarded Message --------
Subject: [[Usatlas-hllhc-l2deputymgmt-doe-l] ] DOE Risk workshop Dec 3
Date: Thu, 14 Nov 2024 12:48:09 +0000
From: Schwienhorst, Reinhard <schwier AT msu.edu>
Reply-To: Schwienhorst, Reinhard <schwier AT msu.edu>
To: usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov
<usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov>
CC: usatlas-hllhc-management-l AT lists.bnl.gov
<usatlas-hllhc-management-l AT lists.bnl.gov>
Dear DOE L2s and Deputy L2s,
We would like to schedule the next DOE risk workshop for Tuesday,
December 3 during the CCB meeting timeslot (1pm EST). Apologies to John
and Hong that this is during LAr week, hopefully at least one of you can
connect anyway.
In preparation, please prepare slides that focus on:
- Risks that can now be retired, or extending the expected expiration of
risks showing as "past"
- Updating the task affected so that all tasks associated with risks are
in the future. - New risks that might have come up over the past 6
months, or issues that are worrying you these days.
- Large changes in probability or cost/duration uncertainty
The current risk register in docDB (#196) is v86, and the supply chain
risk register is v15:
https://atlas-hllhc.docdb.bnl.gov/cgi-bin/public/ShowDocument?docid=196
https://atlas-hllhc.docdb.bnl.gov/0001/000196/105/Risk-Register_v86.xlsx
https://atlas-hllhc.docdb.bnl.gov/0001/000196/105/Risk-Register_Supply-Chain_v15.xlsx
Please look over both for this review. In addition to your slides,
please also prepare updated versions of these registers with updated
cells highlighted.
Any issues, please let me know.
Reinhard, on behalf of your friendly PO
PS: The NSF risk workshop will be in January.
|