Skip to Content.
Sympa Menu

e-rhic-ir-l - [E-rhic-ir-l] Minutes from the eRHIC IR Design meeting held on December 8, 2017.

e-rhic-ir-l AT lists.bnl.gov

Subject: E-rhic-ir-l mailing list

List archive

Chronological Thread  
  • From: Bill Christie <christie AT bnl.gov>
  • To: E-rhic-ir-l AT lists.bnl.gov
  • Subject: [E-rhic-ir-l] Minutes from the eRHIC IR Design meeting held on December 8, 2017.
  • Date: Tue, 12 Dec 2017 17:33:47 -0500

Dear All,
    Below please find the minutes from our meeting on December 8th.

    eRHIC IR Design Meeting minutes
    ---------------------------------------------
          Meeting date: December 8, 2017.

Starting discussion:
    - Bill reiterated that at the last meeting he'd personally attended (11/4) that an issue had been found in the linear optics matching with the electron beam, and that the validity of the current IR design was uncertain. A main topic for this (12/8/17) meeting is to discuss where things now stand, and if possible, push to define and document a modified (as necessary) baseline IR design.
    - A second goal for the meeting is to look at issues relevant to the vacuum chamber/beam pipe design and constraints. Charles Hetzel joined us at this meeting to get a start on understanding these issues.

Walk through of Bob Palmer's presentation:
    - Bob sent a presentation to the meeting list the afternoon of the meeting. The title of the presentation is "Dec 17 IR Update"
    - Notes on Slide #3: the table dealing with the 18 GeV electrons has not yet been updated and checked. Will be updated.
    - Slide #4: What's shown are Bob's beta functions. They have not yet been tuned/matched to the lattice. Steve Tepikian will be working to determine the final beta functions.
    - Slides #5 and 6: Show synchrotron radiation fans, and where they end up. The magnet apertures shown on Slide 6 are rough approximations, and need to be corrected/updated.
    - Slide #7: Again, these are Bob's beta functions, and will be checked and updated to final values by Steve T.

>>>  Interjection of near term need and schedule by Ferdi:
    - By the end of next week (i.e. by December 15th) the goal is to have a "final" set of magnet parameters and geometry/locations, as well as a beam parameters. Also to have a geometry figure showing both the forward and rear regions of the IR design.
    - Brett raised the point that the actual beam pipe, helium enclosure, and cryostat designs for some of the magnets will require actual design to be precise. The idea for this stage is that Brett will come up with his best concept on what the magnet openings/apertures will be for these magnets, and attach some brief text both reminding the users of this information that it requires real design effort, as well as summarize what he assumed in his conceptual design.
    - As there will not be a meeting on Friday Dec. 15th, people who will be updating the relevant tables, plots, or figures, are asked to please send these updates to the mailing list, and Bill will "parrot" them back out as being the "final" versions if/as needed or beneficial. Best would be if when people send the updated versions to the list that they clearly note that they are the final versions.
>>>

Back to Bob's presentation:
    - Slide #9: For the hadron table shown on this slide, by next week there will be one set of numbers for the "Gradient (T/m)" column. The table will also be checked. The electron table will be checked, updated as needed, and finalized by a combination of Steve, Brett, and Bob.
    - Slide #10: Vacuum Outline
        - a "luminosity box" is shown. Elke points out that the design, and then space requied, for the luminosity monitor still needs to be worked out and detailed.
        - Bob makes some comments on what the vacuum pipe/chamber through the detector has to look like, describing where the warm to cold transitions, flanges, etc. may have to be placed.
    - Slides #11 & 12:
        - Shows some of the issues with fitting in the bellows and flanges that might be required for the vacuum pipes.
        - Comment that the actual radial thickness of some of the large diameter flanges shown may be thicker than shown.
        Some discussion that it may be necessary to have welded connections for the beam pipes in some of these regions. Somehow with a design that allows for cutting to open, and then re-welding the connections.
    - Slides #13 & 14:
        - Elke makes the point hat what is shown in the figures as "Tag 1" is not needed.
        - Question comes up about the labeling of some of the magnets in the latest plots and tables with "C" instead of "B". The "C" denotes that these are now combined function magnets.

* Discussion of the next meeting date:
    - Conclusion is that the next meeting will occur on January 5th.
* Preliminary Agenda for the next meeting:
    - Brief discussion and summary of the final parameters for the magnets and beams, as well as forward and backward IR design geometry.
    - Charles reports on vacuum chamber design thoughts/design/status
    - AOB
                        End of meeting



  • [E-rhic-ir-l] Minutes from the eRHIC IR Design meeting held on December 8, 2017., Bill Christie, 12/12/2017

Archive powered by MHonArc 2.6.24.

Top of Page